MCHSBC: Construction Manager Selection and Design Efficiencies - 2026-10-06

AI-generated transcript — the recording is the record.

AI-generated summary. Written by gemini-3-flash-preview from the transcript below, which is the record. It may be incomplete or wrong; it does not report votes. Every item links to the moment it began.

The committee voted to enter negotiations with a construction management firm and approved a series of HVAC, solar, and space-efficiency recommendations to reduce the overall project scope. These decisions brought the estimated total project cost down to approximately $699 million prior to the next design phase.

  1. 5:18 Approval of Minutes — Approved the meeting minutes from September 22, 2026.
  2. 6:08 Contract Amendment for SMMA — Approved a $6,600 contract amendment for a consultant to design a radon mitigation system for the new building.
  3. 10:29 Selection of Construction Manager at Risk — Voted to enter contract negotiations with Suffolk, the top-ranked firm among four bidders, to serve as the construction manager for the duration of the project.
  4. 23:36 HVAC and Solar System Recommendations — Approved an air-to-water heat pump system and a net-zero solar plan using a Power Purchase Agreement for roof and parking canopies, avoiding the higher costs and legal complications of geothermal wells.
  5. 46:52 Kids Corner Program Review — Approved a 350-square-foot increase for the municipal daycare program to accommodate six classrooms spanning infants through pre-kindergarten.
  6. 1:03:12 Medford Family Network (MFN) Review — Approved a program configuration for the family support hub resulting in a 500-square-foot reduction through office consolidation.
  7. 1:13:39 Central Office and Welcome Center Reviews — Approved administrative suite changes and maintained adjacencies for the registration hub, resulting in a net increase of 335 square feet to include district storage.
  8. 1:51:47 Chapter 74 CTE and Teen Health Center Reviews — Approved space efficiencies for vocational programs and the health center, resulting in a combined net reduction of approximately 1,160 square feet.
  9. 2:08:04 High School Administration Review — Approved a net reduction of 603 square feet by consolidating reception areas and reducing the size of the School Resource Officer and campus monitor offices.
  10. 2:25:56 Site and Parking Alternates — Voted to eliminate all options for building athletic fields over parking structures to prioritize solar canopy installation and reduce structural costs.
  11. 2:29:44 Untabling Space Sufficiency Proposals — Approved a motion to reduce a support classroom by 50 square feet while leaving all other previously tabled efficiency proposals off the current project scope.
  12. 2:49:23 Public Participation — Residents expressed a range of views on the project's nearly $700 million price tag, with some praising the recent $150 million in total reductions and others questioning the long-term tax impact.
Back to all transcripts

More from this committee: MPS High School Building Committee

[Member Jenny Graham]: Welcome everyone here and online. Can you both hear me?

[Unidentified]: We can hear you.

[Member Jenny Graham]: Great, thank you. Okay, welcome everybody. It's October 6th at 6.05pm and we're going to get started. Please be advised that there'll be a full meeting of Medford County High School Building Committee in person at the Medford Public Library at 489 Winthrop Street and via remote participation. The meeting can be viewed live on the Medford Public Schools YouTube channel and on Medford Community Media or through local cable channel on Comcast 9, 8 or 22 and Verizon 43, 45 or 47. This meeting is being recorded.

Participants can log in using the Zoom ID, which is 983-8986-8934. The public is encouraged to reach out in the following ways. To the project team for an official response by the project team, mhsproject at medfordk12ma.us. And comments and perspectives that you would like to share with members of the building committee. Those emails are auto forwarded to all members of the SBC. We've received several emails in the last couple of days. And that email is chsbc.medbird.k12.ma.us. I'm going to start by calling them roll. Jenny Graham here. Mayor Lundo Kern.

[SPEAKER_30]: Here joiningly.

[Member Jenny Graham]: Dr. Galussi. Here. Marta Cabral. Here. Ken Lord.

[CAS00002491_SPEAKER_14]: Here.

[Member Jenny Graham]: Libby Brown. Here. Maria Dorsey. Here. Brian Hillier. Here. Tracy Keene is absent and sends his wishes that our project will not have occupancy permit issues as his in the final stages is undergoing tonight. here, here, here, here, here, here, here, here, here. 13 present to absent. I will call the meeting to order. The first thing we have on the agenda is the approval of the meeting minutes for September 22nd meeting. Is there a motion to approve?

So moved. Second. Questions? Okay. I'm going to call the roll. Jenny Graham, yes. Mayor Low turn. Dr. Lucy. Yes. Yes. Yes. Yes. Yes. Yes. Yes. Yes.

[CAS00002491_SPEAKER_14]: Yes.

[Member Jenny Graham]: Next on the agenda, we have a contract amendment for SMMA. I'm going to turn it over to the team to give us a brief update of what the amendment is for so that we can field any questions that the committee has.

[Zoe Moutsos]: So we have amendment number three for SMMA contract for approval this evening. It's in the amount of $6,600. This is in work to get a consultant on to inform the

[Suzanne Galusi]: the Radon mitigation system design for the future project. That's a project of the size would have probably a significant mitigation system.

[SPEAKER_23]: The Radon is a gas-designed one, founded in the ground, especially at ledgy sites like ours. So we think it's important to investigate further.

[Zoe Moutsos]: I will say that there was a test on the current building and that there are Those levels came back with a safe range of radon gas.

[Suzanne Galusi]: But when we are building a new project, there's an opportunity to kick up our radon gas, I guess.

[Member Jessica Parks]: So that is important for this project, short money to design a system of this size.

[Luke Preisner]: Luke. So, uh, much earlier in the process, uh, when we were looking at the, uh, the renovation option, um, I recall. It was an estimate, right? It wasn't based on testing. It was just a precautionary estimate, um, was introduced, um, later. So we saw that the, the rental was going to be 437 million or something like that. And then we added a, HAB-Michael Leccese-Moyers): precautionary rate on litigation some that escalated that price to 12 or five times. HAB-Michael Leccese-Moyers): I want to ask as a result of this consultants work is there a risk that they will determine a system that is not currently included in our city is necessary, in which case, is there an upward pressure on the bottom line price.

[Kimberly Talbot]: So I, I can take that what we've been to pass our estimate was was very conservative, not only under any addition portions of the project, what a new meet may rate on mitigation is going to be planned. But we had also included that in the existing meaning there would be, you know, potentially digging up slab and selling some measures so. As of this point in time, we feel like it's entirely covered in the project. Bringing this consultant on can, one, help us with detailing, recommendations, take a closer look at how best to address the existing portion of the building, and also offer a lot of expertise on cost. So, again, we think this will help us quite a bit as we scope the project.

[Member Jenny Graham]: Any other questions by the committee? I have one question. Will this help us determine the right mitigation from a safety perspective for the future of the building? Is there a motion to approve?

[Unidentified]: So moved.

[Member Jenny Graham]: Second. by Dr. Galusi. I'll call roll. Yes. Mayor Lungo-Koehn. Dr. Galusi. Yes. Marta Cabral. Yes.

[Unidentified]: Ken Lord. Yes.

[Member Jenny Graham]: Jen Belanger. Yes. Libby Brown. Yes. Brea Dorsey. Yes. Brian Laird. Yes. Frayden Keene. Paul Malone. Yes. Nicole Morell. Yes. Liz Mullane. Yes. Aaron Paddick. Yes. Luke Kramer.

[Luke Preisner]: I'm going to abstain.

[Member Jenny Graham]: 12 in the affirmative. zero in the negative, two absent, one abstention, the motion is approved. On to some extensive news, which is about the solution of our construction manager. As you all know, there was a committee established by this body to issue a request for application and then a request for proposals of those qualified firms. And that team has been meeting in a series of public meetings over the course of the last eight months to review application proposal, application documents, and ultimately proposals on our construction matter at risk. This construction manager will be with us through the, for the duration of the project. And we concluded our interviews in the, last few days, a meeting on Monday to look at and digest the pricing proposal and ranking of those firms. The first ranked firm was Suffolk, followed by Kinsey, followed by Bond and W.T. Rich, which was a joint venture, and finally by Skanska. So we had four bidders express interest at the statement of qualifications found, and then again, all four submit a bid, and their technical proposals were reviewed, their centers were evaluated, and then ultimately, and finally, the pricing proposals were opened, and this ranking is sort of the culmination of all of those things.

A couple, I'll offer a couple of overarching comments about the selection. It was unanimous. It has been, was unanimous at every stage by the committee, which includes Matt Grinnell, Matt Rice, myself, Ken Lord, Dr. DeLucie, LeBrown, and Brian Hilliard. A couple of things that stood out about Suffolk and how they became the offerings firm. First, they had a very, very strong technical proposal. Um, and really demonstrated, um, a lot of care and depth in the work that they put together that proposal, including, um, how they talked about the project, understanding of Medford and keeping up. Um, in real time with the work that is happening on this committee that is revolving around things like the deed restriction and everything. Um, and interviewing, uh, one of the things that stood out for me was that they demonstrated a really deep understanding and expertise of the market pressures that we will face as a project. They actually had some rewards, which was nice to hear when you were talking about hundreds of millions of dollars in construction. And they talked a little bit about the scale of this project, how they're already thinking about preparing to bring the right workforce to this project because it is large. and demonstrated to all of us a complete willingness to be a partner that evolves their solution and all the things associated with this project at twists and turns. The buy piece was their pricing proposal, and their pricing proposal was competitive for the value of the service, which is a requirement for a ranking selection in the CMM process.

Any questions?

[Unidentified]: What other high schools in the area have they worked on?

[Member Jenny Graham]: They're just about finished with high school in Lowell. Is it Lowell High School? It is Lowell High School. Lowell High School, okay. They also will be working on the Brockton Project. What's that?

[Unidentified]: They did Thornton High School. They did Thornton High School as well, which is a vocational school to the southern part of the state. Yeah, and Durban, also in Fall River. Maria was something involved with our. Yes, we're going to remember that.

[Kim Talbot]: So we have experienced.

[Member Jessica Parks]: Oh, not all. Yeah, not all of them.

[Unidentified]: It's one of the answers that.

[Luke Preisner]: Luke, so, you know, given the large amounts involved. What were the selection criteria? What parameters did you measure each of these events? And just kind of give us a review. And then was there anything noteworthy in that ranking? Were any firms disqualified from a score in a particular criteria?

[Member Jenny Graham]: So we have to stop short of talking about specific rankings because we still haven't entered negotiations. What we will be seeking tonight is a vote from this committee to enter negotiations with Suffolk. If they're not successful, we will move to the next round. So we have to, there's a bunch of like sort of rules about what is able to be shared at this point in time. All of the things that I talked about were criteria. All the criteria was listed in the SOQ, definitely in the proposal, but we were looking for, firms with a demonstrated ability to do the work that we do both. It's a complex high school, we were looking for people with adequate experience with the complexity of the site, who have experience not just in high schools, but with vocational priming. We were also looking for people who could bring really competitive advice to the table, and they satisfied all of the criteria. All of the firms did a wonderful job. It was actually a really hard decision for the committee. Like I think Paul said, like, we're pretty exceptional people on every single step. And just talk to us and you could tell across the board how desirable this project is. Obviously, it's quite large. But many of them also noted that they are watching our meetings, they're watching how people um, are treating this project and the diligence with which we are going through the process and expressed excitement in being part of this team.

[Luke Preisner]: Um, no, that's fine. You said there's rules prohibiting you from discussing the range. I mean, we have, that's enough for I think any of us. Um, what I want to know is, um, do you look at their proposals and try to measure their performance on cost, schedule, on, um, of a percentage of in-house specialization versus outsourcing. If you can give us some insight into all of the technical aspects of how you made your decision. I think, I'm sure you probably arrived at the right decision, but we just want to know what parameters, or at least I do, what parameter did you use to measure these different firms?

[Member Jenny Graham]: We looked at all of those things. Um, all of the information about the SOQ is public record. So if you want to go and look at it, it's listed right in the SOQ. I'll let the other members of the team talk too.

[Kenneth Lord]: We can go to the top of the news and the... Can you have them handy, Ken? So when we reviewed the non-pricing proposal, we reviewed them on a plan of management and staffing plan, the reconstruction services plan, the construction services plan, the overall project plan, their schedule and phasing. Building information, modeling project logistics plan. Safety history and minority in one employees. And then during their interviews, they were to hike the Medford site, logist challenges and how you'd overcome those challenges. Presented phasing plan, which they all did a butter coordination and community outreach examples of lead buildings completed by examples of budget management and how you approach it. PMB process. and other critical project governance and then you see the biggest challenges. And then we all ask additional questions as they do their presentation.

[Luke Preisner]: Okay, that's great. That's kind of what I'm looking for. Matt and Helen, can I ask, you know, after we made the selection and engaged in contract activities, there's going to be some in the future where estimates that we're currently working with, so 80 months and the phasing slides, those are estimates. probably pretty close to what it's going to be, but it's going to get refined and it's going to be refined through the input of the contractor. At what point in the future do you anticipate that we will have those updated estimates for construction timelines, anything that changes as a result of them sharpening pencils and fine tuning what will be a complicated construction activity?

[Kimberly Talbot]: Yeah, I imagine they're going to jump in right away. I mean, whoever the successful negotiated contract is with, they're going to get familiar with everything MUSO then already have been with respect to the documentation they've had on hand. And they're going to be aging with us. It's, you know, it's the four-legged stool, the four-legged table, the owner, the CM, the OPM, and the designer. Um, we do have, of course, they will be also doing cost estimate mid-December. That set of documents that's going to our cost estimator, estimators. We'll have the two estimates to compare. Those will come back for the end of January. Um, and as far as, um, I don't know what glimpses you were able to get the interview process and proposal process on schedule, if they had provided anything different than our items.

[Matt Rice]: There, there were some, um, Some made, but I think really what we need is to give them the opportunity to us and work collaboratively with the district with ourselves. All that the table to understand where the opportunity are and the updated cost estimates that are going to be generated are directly connected to phase and dual. That's right. But the timing drives Austin a lot of different ways. Um, so we'll have to agree on both the cost that comes out, but in advance that it's going to be a more educated logistic approach as well.

[Kenneth Lord]: And all the firms spoke at length about doing a deep dive right away into our current systems, because they all have to tie into those systems and keep the, you know, the unconstructed areas maintained and the importance of that. And they all had teams of people who. As soon as we signed the contract, we're probably at my doorstep. boring and scanning ceilings and doing all kinds of those, there's really less of the amount of detail that they all spoke about for us.

[Luke Preisner]: Okay, great. So it sounds Florida, like a Florida with a couple updates to off per square foot to why phasing sort of appearing as to this committee sometime in January. So yes.

[Kenneth Lord]: Yeah, that's correct. Yeah. And that becomes our schematic is our actual estimate. We take the MSBA with equal final budget.

[Kimberly Talbot]: That number goes February 10th, February 10th.

[Member Jenny Graham]: Any other questions from the committee? Okay. So we are seeking a motion on termination of the top ranker. And I will await a motion. So moved by Luke, seconded by Lee role. Jenny Graham. Yes. Mayor Lungo-Koehn. Dr. Yes. Yes. Yes. Yes. Yes. Brian Hilliard.

[CAS00002491_SPEAKER_14]: Yes.

[Member Jenny Graham]: Tracy Keene alone. Yes. Yes. Yes. Yes. 13 in the affirmative, zero negative, two absent, the motion is approved. That's a good question.

[Andre Leroux]: Sure. If any of the spring for chosen because of concentration challenges is that we have to come as a committee and motion to get our vote for a second or is that just a pre-expectation?

[Member Jenny Graham]: I would, I would think so. I would want to be able to tell you what happened before we just sort of starting down the way. We don't anticipate that, but if it happens, we'll make sure we talk about it before we move on. Okay. Item number five. So we're going to take a few minutes and hopefully this is like the biggest run of this yet. I'm just exploring the SMMA team. There, for those of you who are interested in sort of the lead up on what we, a brief presentation around our systems, there have been a solid number of meetings of our advisory team, which is comprised of members of this committee, members of city staff, as well as other members of the community with particular expertise in mechanical systems, solar panels, and everything they're under.

They were asked to prepare recommendations on three. One is, what will our HVAC system be? The second is, what will our solar program look like for solar panels? And then the third is whether we will go after sumption of the project being built with MAF timber. That last one has been deferred to the next meeting because the advisory needs a little bit more time, but I'm going to turn it over to Matt to get us through the recommendations for the HVAC system. which is a full air to water heat pump system. That is a change from the base of the project. And then solar, which is a modified option that was previously discussed. So Matt, take it away.

[Matt Rice]: All right, that may turn it immediately over to Martine, but I will also reinforce, reinforce Jenny's comment that we stay brief in terms of the presentation and the information. I will just add that Timber, we had to bring it before this committee today, but we had a very detailed involved on the portable Texas, which did get us to a recommendation. I think Ken described it as a dissertation on portable, but it was just absolutely excellent. And we really appreciate everyone's time. That's been committed to the advisory team so far, because it has been working to the process. And this is how we're working with all the advisory team recommendations from the teams back. Um, to this group, um, and I will ask after Martin done with a quick explanation that if any members of the team, um, that attended those meetings and want us, um, reinforce some of the salient points that were even sort of how we arrived at this, that'd be invaluable for everyone to hear. It's not the consultants, uh, conveying this information, but Martin, if you want to give a quick overview.

[Martine Dion]: sure um my camera is not collaborating sometimes it's fussy with the zoom and i guess it just chose to be right now so i apologize I think, yeah, so the advisory work group elected to go to the air-to-water heat pump for a couple of reasons. One is there's a considerable saving, a first-cost savings, but we did look at cost of ownership. There's also, you know, a savings in terms of the, you know, the three options here all save against the fossil fuel baseline. So from as a basis, and then the ground source seed pump came out as the most expensive due to obviously, you know, the bores are usually the sort of the culprit for that. But in this case, the two geothermal options have a bit more quite a considerable bit more of cost around the limitations of where the bores are going to be located and the fact that we would need a temporary heating and cooling system. So all of this adds up and the savings from the ground source heat pump are not enough to outweigh the original cost. The air to water heat pump brings a good amount, you know, the required amount of efficiency, and they do have a life cycle cost of ownership that is less than the baseline, the fossil fuel baseline. And it's got a considerable initial cost savings over the grounds for CPAP. So that's sort of altogether, I hope I'm, you know, representing what was discussed. That's altogether what led to the air to water heat pump option.

[Member Jenny Graham]: Matt, do you want to go to the next slide just to give people an understanding of what we're talking about? And then for those in the room, I think the folks on Zoom are having a hard time hearing you if you're not speaking loudly. And I think some of the folks in the back also are. So if everyone could just try to use their indoor or outdoor voice. If you have one, that would be great. Yeah, so I just wanted to make sure that people got to see this. The numbers have changed and shifted since our initial look at these options.

[Martine Dion]: Yes, so Matt, chime in as you want. But basically, this shows the initial cost of the system and how it differs from the basis of design, which is the ground source seed pump. So it's pretty considerable at about $31 million. This is the cost of the system and labor. It doesn't have the contingencies and all of that. And Matt, you'll speak to that later. So there's a zero-year payback there. It defers a tiny bit from what the original cost was in the PSR, and that's due to the square footage of the project that has been reduced. And then do we want to talk about the solar, Matt, leeway into the solar?

[Matt Rice]: Yeah, let's talk about the solar as the second item here.

[Martine Dion]: Right. So for the solar, the advisory team or group elected to go for the optimized net zero energy, which would have a roof solar PV and a parking canopy solar PV under a PPA purchase power agreement. That has some additional costs. Those costs are mostly They're mostly relative to the groundwork, you know, the PPA provides for the canopy and all the system, the system equipment, maintenance, et cetera. However, the conduits to the canopy, right, and part of the infrastructure and part of the electrical infrastructure needs to account for the system. And that's what this estimated cost is at. The overall cost of ownership of that approach has a payback of 15 years. So you have this upfront cost, and then the PPA brings you a fixed electrical rate that is lower than your current rate, so you have operational savings, and it takes about 15 years to pay it back. Now, one thing we want to say here is that the PPA utility fixed rate is estimated.

It will definitely differ once a bit. We did our best. We had a discussion with them. It will likely change a bit when the PPA contract will be negotiated. This option does not officially include the battery storage. This is something that could be discussed during the PPA. There are PPAs that don't install battery storage for all kinds of reasons, financial and others. And so that's where we are. That $4 million, obviously, we're going to be looking to hone down on for the schematic design estimate and hone down on estimating it in further detail to make sure we get a more accurate estimate.

[Matt Rice]: So the important thing to find out numbers is when Martin runs a life cycle cost and we're looking at the actual cost of the systems themselves just sort of exactly what it would take to purchase or install the system. You'll see another version of the numbers later on that actually has two multipliers put on it. One of them is leading up to estimated construction cost which builds in things like time contingency and It builds in the contractor's overhead and profit to sort of actually put those systems in as part of the production manager that goes on top of it. And just given where we were at the preferred schematic report, the 40 net multiplier that is constant for all of the cost alternates that we're looking for, all the work that is included in the project. So that gets us up to an estimated construction cost, both in terms of the credit for the air to water heat pump, as well as the cost for that sort of front end of the photovoltaic system. On top of that, we also have soft costs that are being applied at a 22% rate. So that's why the numbers that you're going to see later are a good deal higher than what these numbers are. But this is what came out of the life cycle cost analysis. Relatively, it's all going to be the same, right, in terms of what they are in comparison to each other. But I wanted to point that out in terms of the dollar value. credit rose sprayer pump versus the geothermal system that was originally estimated as part of the project. And because we did not think on sort of basic solar panels on the roof ballast low-ballasted solar panels on the roof there is some additional cost to the size of the electric room as well as put in some underground that go out to the canopies that are provided by the PA for the the photovoltaic. The actual cost to install that 100% net zero energy photovoltaic system is much higher than $4 million. The rest of those costs are part of the power disagreement. The company that puts them in takes on that cost in terms of capital expenditure. And then there's a low operating rate the city receives. It's how a number of buildings and schools within the city already have had solar poofs. It's something that the city has experience with.

In process of that. Okay. I just had one slide that had some summary of the recommendations, the big considerations that were taken on. So yeah, this is a good spot for anyone that wants to jump in from a advisory team or Libby go ahead.

[Member Jenny Graham]: Yeah, I think there's a few, but Libby, did you want to say something as a member of the advisory team or is it a question?

[CAS00002491_SPEAKER_14]: I could do both. I'll start by just saying, I just try to keep up on the meetings. I don't claim to be an engineer, but there are really great people on that committee. So I'm really grateful for them way more than I do. I think we got the right recommendations considering things like, you know, phasing, geothermal and phasing issues. So I really feel really good about the decision we made to recommend these. I have a question about the PB2. I know that, And that's what I'm going to agree on in the room. But there was a question of SRECs that are going to be considered like Sonny brought up. If we're going to be considered net zero energy, we have the SRECs are being bought or like owned by the PPA or the utility. Do we know any more about how that works exactly or do we still need to study?

[Matt Rice]: I'll let Martine chime in. It's a very tricky question. Yeah.

[CAS00002491_SPEAKER_14]: It's, you know, it depends who you ask.

[Martine Dion]: If you ask the OER, they may say no. And if you ask other entities, they will say yes. The SRECs are sort of assumed to be owned by the PPA, but there can be also a, there can be, and Alicia has her hand up, so she can, she can add on, she can add on what I'm gonna, what I'm gonna say. They can also be negotiated to be owned by a city, but my understanding is for Medford, that it's less expensive to have the PPA own this Rex, and then buy, on the market by SRECs. And that would make the project net zero energy. Alicia, do you want to add on and correct me?

[Matt Rice]: Sure, Martine. Can one of you just describe what SREC is, that acronym for folks

[Martine Dion]: Oh, I'm sorry, solar renewable energy certificates. So they represent the green sort of the renewable energy, the green energy that's produced by the system. And that goes into the market to be sold for carbon offsets. Those are what the SRICs are.

[Director Alicia Hunt]: Good evening. Alicia? Yeah, good evening, committee. Thank you. So for those who are not aware, I'm the city's director of planning, development and sustainability and I manage the. City's solar arrays that we currently, we both own some, and we have power purchase agreements. And one of the things with the issue with the idea that electricity and the green attributes of the electricity, which are the SRECs, are bought and sold separately, and they can be separated from each other. Massachusetts State has a program right now called SMART, and it's a multi-year program. We can count on still having it in the future. as we move forward with this, the timing of this project, makes the renewable energy attributes, the SRECs, so valuable from the system that it actually makes sense to let those be part of the power purchase agreement. Basically, even if we were to own this, my recommendation would be to use the smart system, make the RECs go into the smart system, and then separately buy on the market, and I'll use the technical term for people who understand this, Massachusetts class one renewable energy credits, which are like the quote most expensive, to make up for that so that the building is technically net zero as well. This is actually what we did with the library because the value we were getting from participating in the smart system, even though we own those solar panels, it was much more lucrative for the city to get the smart payments from the state. And then we bought 10 years of renewable energy credits for the library to make the library net zero for the first 10 years. And sorry, I didn't prep, but the SMART program only lasts a certain number of years. And at the end of the SMART program, then those renewable energy credits, the green attributes, they revert back to you. So you don't have to buy them for the life of the project, just for the life of when the system's in the SMART program. for the library, we chose to do it for 10 years because that was part of the MSBA and the MSBA, sorry, I'm confusing the terms, MLB, the library built state building program. They required the building to be net zero for 10 years in order to qualify for some of their increased discounts.

So I think, I'm hoping that that answered the question terms that both the technical people in the room who understand the details of this understand and for the general public.

[Member Jenny Graham]: Thank you, Alicia. I saw Tonya.

[Suzanne Galusi]: Yeah, I just thought I think I kind of got addressed. So the reason for the PPA is to doing the outright ownership is cost.

[Matt Rice]: First call primarily.

[Suzanne Galusi]: Yes, thank you.

[Matt Rice]: In producing the maintenance cost for the district over time, I think Ken interested in not taking that on.

[Luke Preisner]: So this choice largely extinguish the risk of article 97.

[Matt Rice]: Yeah, the way that I've been referring to the air water pump is I think it is a win-win-win situation at the lowest first cost. It has the lowest 50-year life cycle cost and does this avoid the article 97 process on the deed restricted land by having to put the geothermal wells underneath it. So I think all the way around, it seems to be really good. It makes a lot of sense. Yeah.

[Member Jenny Graham]: Any other questions, Brian?

[Unidentified]: I have a question for you, Martine. You mentioned the battery storage. You even had a ballpark on what that would cost, how that impacts things, and actually change the life cycle or the return on investment at the 10-year number.

[Martine Dion]: So the battery storage going to the PPA, that's going to be part of the sort of the contractual discussions with the PPA. They would be the one to decide if there should be a battery or not. That said, I think that the project should make sure that it's battery, to have the battery readiness. In the case they don't support it right away, there's a high chance that in the future the economics are going to make it better. I think currently what they told us is that the market for them makes it challenging to have battery storage. So that's all going to unveil, I think, itself as the discussions with the PPA would go.

Your question cut off a little bit, so I'm not sure that I'm answering exactly what you asked for completely. Can you let me know? Did I answer your question?

[Unidentified]: Thanks, Martínez. You got it. My other quickest component of that was whether or not having a resource system changes the dynamics of the payback in 15 years?

[Martine Dion]: Yes, it does. It does because it's another, it's, you know, owning it is about 4.5 to 5 million dollars. So if you own it, it would definitely change. If the PPA includes it in their PPA, it may change their fixed rate. And that's something that would have to be discussed with them. If they put it in, it's because it's going to be beneficial for them, and it should benefit the rate. I don't think they're going to do something that's going to not be beneficial for the fixed rate to be good for the city of Medford. That's my understanding. If they decide it's not in, it's because it's putting an impediment on the good financials of the contract.

Did that answer your question?

[Andre Leroux]: Yes, thank you.

[Member Jenny Graham]: Any other questions? Is there a motion to approve the HVAC and solar recommendations from our advisory committee?

[Unidentified]: Motion to approve.

[Member Jenny Graham]: By Aaron. And seconded by Brian. I will call. Jenny Graham. Yes. Marilyn O'Kern. I move. Dr. Galuzzi. Yes. Veronica Brault. Yes.

[Nick Giurleo]: Yes.

[Member Jenny Graham]: Jen Belanger. Yes. Libby Brown. Yes. Maria Daugherty. Yes. Brian Hilliard. Yes. Tracy Keene. Paul Malone.

[Nick Giurleo]: Yes.

[Member Jenny Graham]: Paul Morell. Yes. Lynn Haines. Yes. Aaron Alvarez. Yes. Luke Price.

[Nick Giurleo]: Yes.

[Member Jenny Graham]: 13 affirmative, zero negative, two absent. Those recommendations are approved. Okay, moving on. So the next section of the agenda, for those of you who may or may not have joined us in the past, is part of this project agency review that has been going on really since PSR was submitted in June. And it's really starting to say things like, how does the layout in the building inform whether there are sufficiencies that we can face? And we have been making our way through all of the various like components of the space summary, section by section. Tonight is the final piece of that discussion. So what you will see in these upcoming slides is a presentation of the work that the district educators and the project team have been doing together to look at space efficiency as it relates to Um, two things, one of holding the ed plan and two, um, where, where things are located in the building start to matter when you're talking about, um, whether there is an opportunity for any efficiency. So those things happening sort of tandem. Have been the subject of like probably close to a hundred meetings at this point. Um, and we have been reviewing by section. So in this section of the meeting, we are going to review. the collation of that work on the topic. So we're gonna take them one at a time and we will make questions and comments from the building committee. If there are members of the public who would like to speak on those recommendations, we will have time and space for you to do so. There is another section of this agenda, which we'll consider untailing some period of time Proposed cuts that have not been yet made and come later in the agenda. So if you are, this piece is dedicated to the folks who have been doing this very hard work to get through all of the spaces in terms of like how these things are located in the building and to see like, let me pick up some of the proposed plans that are happening in various components of the building as well. So with, That said, let's start with Kids Corner. I'm muted first.

And I will turn it over to you.

[Matt Rice]: Right. We apologize in advance. There are a lot of slides here. We've tried to include some graphics where it makes sense just so that we can ground people and where the proposed program is going to be located. But for some of these, as we move forward, we don't have those diagrams just because these places are going to be located all over the building. This one, I think, is going to be grounded. The plan image on the left-hand side is of the southern side of the building. It is located on the first floor. And we're depicting there are the various classrooms that constitute the proposed kids' corner space. And I will just provide this clarification once, but it's going to hold true for all the diagrams that we see. of these very much an early iteration of where we are. We're really at the conclusion of the programmatic report phase. All of these plans have been modified based on the feedback that we've gotten. We are not showing our updated plan because we need to have these conversations. We're finalizing all the reductions so that we know all the parts and pieces that are put into the building. Then we can come back and we can make sure that we're providing final locations and bringing everybody's feedback into them. This just gives you a frame of reference in terms of where are the general print releases that we're talking about. But the most accurate piece of information that we'll be reviewing are the tables that actually have the list that are proposed, as well as any efficiencies that were identified through the programming decisions that we've had. I know that some folks this is going to be familiar to because we have looked at this process multiple times, but I also know that we have folks who have invested in us for this particular iteration.

To go through the list of spaces, what I just want to start off by noting that the key corner spaces are not reimbursable space by the MSBA. They are in the other category, which just means that it's not contained within the typical school. And so if it's not within that particular grouping of spaces, it's a non-reimbursable. So that's just for an understanding of what we're talking about. We did talk through with the Kids 4 Leadership. We understood that the number of classrooms that we were holding previously was not exactly aligned with how the program does implement. And so really what happens is that there is a younger and older infant room, there is a younger and older father room, there is a preschool room, and there is a pre-kindergarten room. So there was a need for 6 classrooms. We previously had identified 5 classrooms total. So what we did was we reduced that larger 1,200 square foot classroom count down to 2. Those were appropriate size for the preschool and for the pre-K classes. And then we added in what amounted to 1 additional toddler classroom. And basically converted over 1,200 classrooms into a 900 square foot classroom. The two infant classrooms that were planned were also reduced in size from 900 to 900 because that matched the overall collection in typical classroom sizes is still more than adequate for the planned enrollment for the Kids Corner class. So you see that there is overall we get all the way down to the bottom of the modifications. Even though we're looking for efficiencies, we also need to make sure that we're adequately addressing the need of the program. And that was one of the conversations that I had. So overall, it was a 350 net square foot increase. The other reduction that was made though was in terms of the number of offices that were planned. So we had originally planned for two offices associated with the program, and we were able to identify that. only one office would be needed. And so that factored into the overall math. So there were some addition, there were some addition as well, which resulted in a total increase of 350 square feet for the overall program.

[Member Jenny Graham]: Are there any questions from the committee?

[Luke Preisner]: Luke? So I'll just observe that. Currently we have a kid's corner program at the high school. I don't think it serves infants. It really serves. And so I wanted to ask, one, whether square footage represents expansion over the current program. And I wanted to better understand the staffing needs. If we need an office, I kind of understand that. I don't quite understand the staffing. maybe the conference room. I mean, maybe boss can hold court, but probably in the main room where all the other, I guess I don't understand why it's a conference room. So if one can shed light on that, I'm all ears.

[Suzanne Galusi]: Patrick Lewis, I'm happy to shed light on that. First of all, just to remind anybody that's like here or joining in this municipal daycare. So it serves our employees, both on the school side and city side. It also community members. So if you were to go to this space, it is very, very small and it. This will allow us to serve more families. There's a little bit of a wait list to be able to meet the demand of some unity members. Right now you have like one, let's just say for intensive purposes, you have one classroom that's being shared by like young toddler, older toddler. It's quite tight. There's not a lot of space necessarily for equipment and movement and materials that students need to you know, interact and engage with so that they can like grow and develop into lovely little humans. So that's first of all. Um, there is each spin, um, a younger and an older, so there is a toddler and there's a pre preschool and a pre-K. So servicing nine months.

[SPEAKER_03]: You can start at two different months.

[Suzanne Galusi]: two or three months to five years. That's the span for kids. Right now, they have a office for the director. There is a staff room. People have to be able to eat their lunch and take a break. That is what the staff are, you know, phone calls, private telephone calls. So that's what the staff is used for. And then the conference room, the staff here conduct like any educator does with teacher conferences. There are staff meetings every month, and there are evaluation meetings that the director is having with the staff. So the use of a conference room is important for at least all three of those reasons.

[Luke Preisner]: And there aren't any opportunities to share different rooms with co-located programs, so need break there. Um, Kirk might be, or maybe right down, right upstairs. Um, what was looked at, um, opportunities to share because you have a very large structure. And, you know, I think this school is large as it is because when it opened, had to serve 300 kids. And when those enrollments fell, like they're around 1100 now, It freed up a lot of space. And I don't have a timeline. I don't know when these initial programs started. I don't sort of, I'm not dissatisfied with the programs, but you know, we have a hundred high school students that should, in my view, be the top priority for this project. And- I don't disagree with that. And so this, I guess, a little disappointed that we can't find opportunities to share resources for the non nine to 12.

I'll say, members of this community, because we are real much people that construction costs have gone up. You know, so every square foot is like 1000 bucks, it might actually be more when Suffolk sharpens their pencil and gets down to it. I may find it's actually significantly more. So I'm worried about that because it drives a bottom line cost that I think too many people may not be able to stomach.

[Suzanne Galusi]: I would also like to add. So one of the things that has happened, first, there's the piece about, honestly, like the core values of the district and the community. I would say my children went to the corner. They are 23 and 22. It has been around in service of our staff for a very long time. It was something that we'll get to probably further on in this. But there are many teachers that don't have the benefit and employees that don't have the benefit of preschool programming. And there is enough preschool programming. And even our preschool programming had a lot of barriers for families. So I found that myself. And so a program like this is very important to help our teachers do what we want them to do in service of our students. That's, that's kind of first and foremost. The other piece about this program and the ECC in general is that our early Childhood Program for CTE. They work with all three of these entities. So there is, we have dissolved the Make Way Kids program that was tied to the CTE program. And this is the program our students are also learning through. So Kids Corner, this way, our CTE students see what possible pathways there are in the early childhood education portfolio of job appointments. So you have a daycare setting at Kids Corner, you have nonprofit for MFN, and you have teacher-tracked education in the preschool program. And right now, they are working directly with the director of Kids Corner, which is and could be of use for that, for all of the spaces here that are listed. because our high school students do benefit from these programs.

[Member Jenny Graham]: I'm just going to offer two other quick comments. As on the school committee who has been charged with negotiating with all of our labor unions, we negotiate with the Kip Warner team, and there are some like really unique things in their contracts. First and foremost, because of the nature of the work that they do, They don't get a guaranteed like duty free lunch. They, they have a paid lunch and they are nearby because kids are unpredictable. These are unpredictable and we call on them when we need that. So they have a very unique situation. They're the only employees in the district by knowledge that have such a unique situation that their, their lunches are paid for under their collective bargaining agreements. I think that's like sort of the number one. Item two is. The cost to operate Kids Corner is completely operated out of a self-sustaining revolving business. It's not operating budget money from the school district via allocations from the mayor's office to Medford public schools. This program is entirely funded by tuition paid by those people sending their kids to school. I think there can be a lot of confusion about some of these programs and where the money comes from. I just wanted to make sure that was clear.

[Luke Preisner]: And I just want to say, I think that this program or that network or that none of them are at risk, all in the airplane. They're guaranteed to have security. What I'm expressing is just the disappointment that we can't find more conference rooms, storage rooms, and so on. because I think we're pretty desperate for space issues. That's the only point I'm making.

[Member Jenny Graham]: Are there any other questions or comments? Libby?

[CAS00002491_SPEAKER_14]: I guess I have a bigger question. So as this is turned into real architecture, I mean, this is real, but still very conceptual. You know, I know this is tied to our ed plan, but say like what Luke's describing, as you figure out the instances, you know, you see, oh, you know what, the comfort room could serve groups because of where it is and the way, how often they're using it. Like, if we see that the education plan, like the needs of the programs are being met, but it does say like eliminate room because the adjacency makes it work. I know we've talked about, we can't like remove space later because that changes the ed planner, changes like our program. I don't want to break any rules with the MBA, but like are those little as long as we're showing like we're meeting the needs of the program, like little changes like that. Is that okay? Does that spread flags?

[Matt Rice]: I think we will have to find those types of things really over the course of say the next two months as we prepare the cost estimate and sort of the final iteration of the plans to be submitted because after that point it becomes more challenging to do that type of thing. So would have that opportunity, would need to run any sort of substantive opportunity past the occupants, past leadership. Sure, of course.

[Member Jenny Graham]: And I just want to reiterate that that's what just happened. That view of like what's needed to operate this program, that is the conversation that is creating these recommendations.

[CAS00002491_SPEAKER_14]: I don't need to say it like or asking for something that's not, that's not what I need to say.

[Suzanne Galusi]: No, but we can answer the next slide. I can add, I can also answer and add on to what you are saying.

[CAS00002491_SPEAKER_14]: It's hard to say, like, well, they care, but they, those are the groups that are, it doesn't work. But I might be asking myself, it's very hypothetical and may never cut the message. It's just curious and kind of weird.

[Member Jenny Graham]: Any other questions? Is there a motion to approve these recommendations? So moved. By Nicole. Is there a second? I will call the roll. Jenny Graham. Yes. Mayor Lungo-Koehn.

[Mayor Breanna Lungo-Koehn]: Yes.

[Member Jenny Graham]: Dr. Gouldy. Yes. Marika Brown. Yes. Ken Lord. Yes. Cindy Brown.

[CAS00002491_SPEAKER_14]: Yes.

[Member Jenny Graham]: Jill Langer.

[CAS00002491_SPEAKER_14]: Yes.

[Member Jenny Graham]: Maria Northey.

[CAS00002491_SPEAKER_14]: Yes.

[Member Jenny Graham]: Brian Helliard. Yes. Tracy Keene. Paul Malone? Yes. Nicole Morell? Yes. Liz Mullane? Yes. Aaron Olapade? Yes. Luke Preysen?

[Luke Preisner]: I'm disappointed. If I vote no, then that means voting to revert it to a new size. So I'll just add that.

[Member Jenny Graham]: 13 affirmative, zero negative, one absent, one abstention. Motion is approved. OK, next.

[Matt Rice]: All right. So the next program for discussion is the Third Family Network, or MNBEN. This space is located immediately adjacent to Kids' Corner, so if you're able to acclimate, I'm still on the first floor of the building in that southernmost wing, where the sort of shared early childhood resources are going to be located. The kids corner the Medford and Lee network spaces are not reimbursable by the MSDA because they are not in a sort of traditional MSDA guideline high school building.

Spaces that are included here are a reception waiting space. There are two offices that are also doubling as testing spaces. There is one shared office that has multiple employees that works so a more efficient way of seating folks. A conference room dedicated to MFN. The play area, which is really the centralized program space for FM programming that houses different play groups at different ages to allow families to utilize resources. There was previously a pantry space that had allocated for Bedford Family Network that through discussion with leadership and disleadership was identified as not being required, so we removed that. Um, and some of that storage capacity, um, was consolidated into that last line item. Um, so we removed, uh, a 300 square foot dedicated line item. We added 200 square feet into the general storage room, which will provide a general storage resource. The clothing closet was a fund that was entirely not, um, utilized by Medford. I think it was just a misunderstanding on our end during the initial conversations. So that was removed. Um, and then, uh, there was a toilet room that was dedicated well, and it was discussed that that toilet room, those toilet facilities would have been for Bellamy network that general toilet rooms out all the way in the immediate vicinity of MFN could be used as well. So that, that program at area was removed from the overall sum total. And so all the various adjustments that there, uh, result in an overall reduction of 500 square feet, uh, for the MFN.

[Member Jenny Graham]: Any questions?

[Luke Preisner]: So I just computer away. I can't check myself. Um, but it looks like we're how I think when you add up all the space, it's bigger than what we have today. Or am I just sort of misreading it?

[Matt Rice]: It be true. I have not memorized all that. I don't know if folks have the numbers in front.

[Suzanne Galusi]: I think the piece to this, which also goes along to your question is, and what you were saying earlier with that, I think, you know, over time it was space. I think there was like, you know, uh, spreading out or moving into other spaces. So you have the immediate MFN, but if we go outside the right now, currently the immediate MFN space, there are four or five. other offices. One that's specifically used for the testing that is mentioned here, that's part of one of the grants and one of the requirements. And then there are other offices, play group leaders, assistants that also have space outside of what MFN is. So this is kind of consolidating all of that. So part of the reason, and of course we are open to what kind of like ebbs and flows from this in terms of what Libby mentioned. But the use of the conference room for MFN specifically is very much on purpose because they have a lot of staff that come in and out and a lot of caregivers that volunteer time. And so their use of a conference room is very different than kids' corner use for a conference room. in not always, am I wrong to say, a scheduled manner. A lot of it would drop in and out. The parent education pieces that are in the conference room.

[Matt Rice]: Susan, I can clarify. So Helen helped actually brought up the numbers. So we're about 800 square feet of production actually in terms of overall footprint of what happened now and what proposed here, which is about a 20 to 25% reduction. So there is a fair amount of efficiency that was arrived at here talking through again to make sure that we're providing sort of essential components of the program as we move forward. I guess if it would make sense to have a little bit of explanation of the actual family network is just so that folks that are listening can understand the value of the resource because it's as simple as like a daycare. We all know what daycare is I think generally, but I think MFN is a more unique.

[Suzanne Galusi]: Can I invite, I'm going to invite Dr. Ott. You do much better than I can.

[SPEAKER_03]: Hi, thank you. I was kind of prepared to talk about something else, but okay. First of all, I just wanted to, if I just read a little bit of what I wrote, just want to introduce myself. Karina Shumway, Medford resident, also a parent of two Medford High School graduates and currently director of Medford Family Network. And I just want to begin by expressing my sincere appreciation and an immense time and effort and hard work this committee is dedicated to this product. So to just give a little bit of a background, over 33 years Metro Family Network has served as a welcoming front door, purple door, community hub for thousands of children, caregivers and growing families.

And we've sort of, you know, working, worked alongside with corner, you know, so as we were kind of in the beginning stages of, you know, this early adulthood center, being a part of that has been really integral. And I kind of also a little bit about, you know, our connection to Medford High School and You know, what being in this building has meant to MFN. We work with the Registration Office. We've had families come directly from the Registration Office being logged to MFN for route on the court with diaper cleaning assistance and parenting resources.

We've had high school nurses come and connect, that team can do things directly to us for support. We've had special education and transitional students that volunteer with us. break groups, sorting donations, with diaper days, building essential life and job skills. We also collaborate with the vocational programs at the Graphic Artway Kids. You know, by being housed at the high school, we're able to provide, utilize the gym for family fun nights that we do monthly. We use the theater for still programming, um, you know, for peer education classes. Um, and, you know, we're backed by school security and historical support. So we're a program that serves Metro residents who haven't been found from birth to age eight. And we provide programs such as plan learners, education classes. We do a lot of concrete supports like for days, like I mentioned. where we see anywhere from 70 to 90 families come through our door and everybody's given day wipes, toiletry items, food, bags, clothing. We have partnerships with organizations like the Crayons and a variety of other places where we're able to kind of reach those partnerships and we're able to get donations from them that we're able to directly send families. We also have a very a volunteer base of the Friends of Method Family Network, their fundraising arm of our organization. We have an advisory board, all these groups of people in the conference room, and they help us kind of be what we are. We attend a lot of community events in the city. We partner with our Welcome to Kindergarten programming. We do a lot of kindergarten ready play groups. We actually partnered with Boston Children's Museum, and we're able to do curriculum-based play groups that get the children ready to enter kindergarten and go to school.

[Member Jenny Graham]: Thank you, Irina. Are there any other questions about FMN and the recommendations before? There are a moment to accept the recommendation. Motion to accept. Seconded by Liz. I'm going to call the roll. Jenny Grant? Yes. Mayor Lungo-Koehn?

[Member Jessica Parks]: Yes.

[Member Jenny Graham]: Dr. Hersey? Yes. Marta Cabral? Yes. Ben Lord? Yes. Jen Belanger? Yes. Libby Brown? Yes. Maria Dorsey? Yes. Brian Hilliard? Yes. Tracy Keene? Yes. Paul Malone?

[Nick Giurleo]: Yes.

[Member Jenny Graham]: Nicole, yes. Liz Mullane, yes. Aaron Olapade, yes. Lou Geisner, yes. 14 in the affirmative, zero in the negative, one absent. The motion is approved. Next topic is central office.

[Matt Rice]: All right, so we go ahead and plan images here. Central office is primarily located above the Early Childhood Center, those areas that we were just looking at. Um, I will point out though, that there's, we'll also get the welcome after this. Um, sometimes those both fall under the umbrella of central office, but a welcome center is more of that parent information centers or the family forward facing, um, set of services that are provided. Um, central office is helping incorporate the superintendent's office, all of the administrative personnel, well, uh, facilities technology. Um, so we'll run through all of that. I don't know if it is it worthwhile for me to run through everything that does not have a modification here just so everyone's aware of what's in or shall I focus maybe just on the modifications that occurred or we can go back and ask questions. I'm only asking so that we have sort of mission path forward as we go.

[Member Jenny Graham]: Maybe Dr. Luzziqa would like a quick update of what central office is for the district and that are there and then we can focus on what's changed.

[Suzanne Galusi]: Sure. Right now currently housed at Medford High School what is as of sent to office would be all of the senior and district-wide leadership offices. That includes just in a nutshell I would say like myself the assistant superintendents. Other members of the executive team are Ken Lord our operations officer. Will Papaselli our communications director. We also have up here. the directors, but like pieces that are under Ken's which is IT, security and facilities. We also have human resources up here, which is a place that not only our employees visit, they have questions about some of their benefits or a need to change some of their benefits, but also any worker vendor, caregiver that we need to complete a court in order to be in our schools, to volunteer and or work. That also includes office and director. And it also includes our finance office and our payroll. So those also two offices in which employees visit. And in addition to that kind of wing, central office, we also have our district-wide directors. So that's all of our content directors. We have our communities, math, science, PE and health, art, nursing, world language, technology. And I talked about the welcome set too, but do you want me to wait or just... Wait until we get those slides, yeah. Sure.

[Matt Rice]: Yeah. All right, so through the efficiencies were found and working from the top down. The copy all room was determined that it would be 100 square feet smaller, still serve the function that it needs to. So that was one efficiency that was noted. Superintendents, I think probably got in there from our standard list of things that show up sometimes in central office suites, and that was immediately taken away. There will be ample toilet rooms located around a building. It is not necessary. If we go down to the bottom of the page, the next one in terms of the director's open office. So this is again sort of an open bullpen style office where all the academic department directors are co-located. Right now there are individual offices in the building because and just moved into the available space that was around, but this will provide a more efficient configuration for everyone. We did increase that by 100 square feet because we took one of the directors out of an individual office that was sized at 150 square feet to be on the next page. So there was overall an adduction of 50 square feet by getting them co-located in that centralized director's open office. The next item is the same total area in terms of 200 square feet. There are two individual offices previously, but what we're going to be doing is having a reception area and a waiting area for outside the director shared open office, because it was seen that it's just not appropriate to have somebody walk into that bullpen open office. So there is an administrative assistant assigned to the directors and so that 200 square feet will accommodate some amount of production collecting as well as a workstation for the administrative assistant. The director's conference room was reduced in size by 50 square feet just given the size of the meeting that would be taking place in that particular conference room. If I go to the page maybe one more after this as well.

If we go down to the payroll open office, so that is again separate for the finance group of their own office area. Each of them are separate from each other right there. We're combining directors as well as payroll. That space can be a simple size in terms of the amount of space required for four individuals within an 80 square foot per person. That's how we got down to 320 square feet. Under technology, there was a redundant position, a sort of binding of roles that happened. So it was identified that that technology director office could be moved because that was the director. Oh, sorry.

I'm talking about the network administrator. So that the district technology director is the one that was moving up into the shared director offices, right? So this was the 100 square foot office. that became 100 feet within the shared environment. And the network administrator was consolidated with the position that's on the line directly above it, the IT manager and network admin. So that 125 square foot dedicated office was removed. Then lastly, as we were going through discussions, it was identified that there was a need for a district supply storage room, which exists here currently at the building. It's located below the gymnasium. It is one of the spaces that has grown to fill the space that was available. Um, so it's much larger than it is right now, but currently in terms of distribution of paper goods, um, so out to the rest of the district, um, those slides are delivered here and distributed out, um, uh, standing operating procedure. They're needing some repository for space that here that was not identified when we went through the report. So again, we, add up all of the fishies as well as the additional need for that storage room, we get to an increase of $335,000. Questions from the committee?

[Member Jenny Graham]: Luke?

[Luke Preisner]: I have to ask about the phone booth. I mean, Dr. Oon didn't have a 40 square foot phone booth, right? Can you explain what a phone booth is? At work, I'm familiar with these like calling pods. Yeah. They don't count against square footage or just kind of in the hallway. Yeah. Tell me what a booth is. We have a lot of them by the way.

[Matt Rice]: Right. Yes. And they are a by-product of even office culture, right? Anyone that has sat in an open office of any, you know, that you can't have a private conversation. And sometimes you still, if you're in zoom meetings all day long, you need a place that you can have acoustic privacy. And so we have those sort of as well in our office lots of meetings inside of the The reason they're 40 square feet here, and so the ones that are in probably everyone's office, they're about 16 square feet. We actually measured them today, because I was just curious. They're about four or five square foot. They're not wheelchair accessible. They're not handicapped accessible. So you need a room, and 40 square feet is not a big space altogether. But you do need, from an equity standpoint, to provide that resource located throughout each of the buildings. the office suites where we have offices and we're relying on that efficiency that we get in the open office to have those private conversations.

[Phil Santos]: So I see there's, I think that one more page. There's a conference room at 250 square feet, but then there are multiple offices at the same size, but what's at the conference room seems to be a little bewildering to be also the size of an office. There's more people in that office, is that?

[Matt Rice]: Yeah, so there's different sizings based on the length of the different offices. So usually when we see 250 square feet, that's a desk in an office, but also a small conference table, so we don't have to have a separate conference room. how they're used today. And there's just a large frequency of people coming in need to meet in groups of like four to six, typically that in that type of office space. So that's stabilized. Okay.

[Phil Santos]: I guess we, the conference rooms that couldn't be used and then kind of keep the office a little smaller because some of the offices are smaller, obviously, right? They're like 150, 125.

[Matt Rice]: I can let the district staff speak to it, but generally it was, we're basing it more or less on the model of how things are used. And so there's frequency of the meetings that are earning. It's enough to keep both that conference dedicated conference room occupied as well as individual office to have the conference table in them. Okay.

[Suzanne Galusi]: Yeah, the only thing I would like to say, chime in, chime in. We need to collaborate. And there are a lot of committees, there are a lot of team oriented type meetings, both within like central office, but also within administration district, a lot of joint committees with our bargaining partners, which, you know, and our staff, but then there's also means that are confidential, that That is how we are using spaces now for flexibility. And I would say that we often run into, uh, overlaps and us trying to, you know, find other spaces, maybe around this area, like library, because you're just, right now we have like two spaces, which are about the eyes. Um, do you want to reveal anything you want to?

Luke?

[Luke Preisner]: Well, so the offices of mine, I have an office at work. I'm not very important, but it's like 12 by 10. And so, you know, seeing, and don't take it personally, but, you know, seeing probably like four offices, there's another one next page at 250, kind of jumps out. I guess I could understand why like one, maybe two or five, but I'm a little disappointed to see so many of them. And also a little disappointed to see an 800 square foot conference room. 800 square foot is like the first floor of an average man's house.

Pretty big. And so again, just a little disappointment that we couldn't find efficiencies because we're an enormous structure for 1200 high school students. principally, and then it's all the extra amenities that we're adding in. So expressing disappointment.

[John Falco]: It's a big conference room, I would agree. The SuperCats conference room, which I don't actually know.

[Unidentified]: I know, it's a square footage of that.

[John Falco]: It should just have like a blaze in the background. I know. It's not big enough. I've been to rooms, meetings, where everybody's around the table, then everybody around the wall as well. And there's not enough for all of us. I think that you have a group of people around the table, then you have a group to sit outside the table, but not separate. Like it's all of us are trying to have a negotiation. Them being second tier seating is certainly not collaborative. And they're all just, they have just as much right to be folks who arrive to get a spot at the table. And we certainly have negotiations where there isn't room to even be in the room. So it can be six hour long negotiations.

So I think having a reasonable and appropriate base is important. I know that at It is a big space, but it'll also say many things where we're going to go to the superintendent's conference room, and it's already booked, and we're all going to go to other places to have a meeting. That's sort of like the regular thing here, that there's just not enough conference rooms. The general conference room, we don't always need it to be big, but when we do, it's a real one that we're hunting for classrooms that we could try to switch into. That's been my experience. Obviously, I don't work in the building on a day-to-day basis, so I can't speak to professional development or whatever other kinds of things you might have going on, but school community events, in my experience, is constantly not enough room and not enough tools.

[Matt Rice]: So Helen did show us the square footage, which I'm learning. So we'll just go to Helen for all the questions. But 542 square feet is the size of the existing one. I do recall that Mercedes was saying it was exactly what Paul was alluding to, is that there were many uses where it was not sized sufficiently. So we talked about what is the sort of the maximum number of people that we need to accommodate in the room, the size of the concert room accordingly.

[Luke Preisner]: Thank you. I've got a follow-up question. Sorry. So the only thing that came from COVID was this proliferation of virtual conferencing systems. We have Teams, we have Zoom, we've got Wex. I'm probably missing some. To what extent was modern video conferencing baked into some of this room sizing, or just was it not?

[Member Jenny Graham]: I think Dr. Galoos, you should answer that question of the stature and expectations here.

[Suzanne Galusi]: Yeah. Are there opportunities for that a hundred percent, but this is the work collaborative hands-on, you know, I was going to use the word almost, but many meetings are in person because there are artifacts and iterations and sticky notes and part paper and like. thoughts and ideas live on whiteboards and coalescing and creating, like that's the work of education. It's not, there are opportunities essentially where every third grade teacher together during their prep time across the district, we're going to want to zoom and we're going to be able to do that. But if we are talking about, um, Negotiations or Ken's safety meetings or Ken's meetings or Kim's, um, teaching and learning meetings when Marta wants to grab all of her people after school, like they're in person because we, we are working together on shared work. It's just, I feel like I'm having a bad time, tough time myself, but it's not. work, it's always uncivil.

[Luke Preisner]: And it sounds like it's cultural. I mean, you know, I, I work in an industry that involves collaboration and complicated activities, um, occasionally negotiations, uh, different culture, uh, we're geographically, uh, separated. Um, and so perhaps there's a great incentive to be able to collaborate and be effective. even if it's complicated. So anyway, thanks for answering and providing insight to the culture.

[Unidentified]: Any other questions, Lisa? I was just wondering because 800B is a big space. I don't know how often it fills up. I know that it's clear that 80, but there's also a lot of spaces in the new building that I think are kind of supportive of collaboration. And I'm just wondering, are other spaces, I'm thinking about the large room that's near the new auditorium, like the room there, are other spaces that could serve that purpose if it's happening all that frequently? So I guess I don't know if it's like a twice a day thing or a once a week thing or, you know, once a month. And if there are collaborative spaces that could roll off.

[Kim Talbot]: So, thank you. So, the priority, I think we said that this earlier of the building function of this thing is for the school students and their teachers to really use this whole thing. The guidelines are that class have to be used 5% of the time. Talking into a new classroom or an unused space. It's going to be less likely to happen a new building as it is here. And this part of central office is to be separate, not to be mingled throughout the high school experience. And so I would caution against having an overflow space for central office function actually be designed for students to be 20% of students in the school space. We do use the conference rooms all the time. They are always used. extra space in some of the larger offices with the smaller conference tables are used constantly. And we are still strapped to look for space that doesn't, on a regular basis, that doesn't impact the regular teaching and learning that happens in high school buildings. I think in previous iterations already, we've created some reductions in the number of conference rooms that were originally assigned to central office. And so this is sort of what we think we can live with and still be the weapon of the district and not impact the really important flexible work for teaching and learning that are in the high school floor.

[Suzanne Galusi]: And you know, you could look on its face at the 800 square feet, but the other side, just like the operations of things that happen day to day, is the adjacency having two conference rooms In central office, we have 11 bargaining units. In negotiations, we need both conference rooms. Sometimes there are also issues that involve staffing, legal meetings. Aside from the teaching and learning, there are the other pieces to what happens in central office that having conference spaces more than one and located within the same kind of adjacency is just needed and critical to the overall functioning.

[John Falco]: This also represents less conference rooms than we have now. We have the very large conference room that is in the hall right here. And then between the superintendent's office and the finance department is an even larger conference room. And those two are not enough. We're getting less. So I won't be involved. I wasn't involved in the conversations to decide we can have less. But we are doing negotiations. We're in a room with our own team and the team of the union. Where we need 800. And then we caucus. So we all on our team get up. leave and we go to another conference room. So we can talk about what we want to talk about, they can talk about what they want to talk about, and we're back and forth and back and forth. And sometimes a lot of times. So that's two conference rooms that are immediately available for any other administrative activity going on at all. Like, we don't want to start an end time off. Sorry. But that was long ago. So we can't be using a space that has land special about or some other group is planning. So I'm a little disappointed we're gonna have to, but I think the ship would sail when that stops. Thank you.

[Member Jenny Graham]: Are there any other questions about the central office changes?

[Michael Pardek]: Paul? I have two things. I actually support constantly rooms. This is an organization that has most of that. I was like, they're going to need a conference room. But within a little collective bargaining, I would say the hull between the two separate caucus room being adjacent was where there was like the difference between the union saying yes or us being stuck forever. And I think that is a very, very real thing. And I had to do that work. I can't imagine what it would look like.

My brief time working in an organization with Boston Public Schools, where it really pains me that none of this is reversible. But my brief time working in an organization that worked with Boston Public School, where I worked with incredibly talented and hardworking people in the central office, and incredibly talented, hardworking people who were principals, administrators, teachers. The really sad thing was that the central office didn't have anything good to say about that from the principal admin side.

on us versus them as their worth is really disappointing. So I don't wish for anything to reduce any of the space, even though it is. I wish that we'd built an admin center on this campus 20 years ago when there was construction costs weren't so expensive so that we wouldn't have to be dealing with this. But I don't see any alternative. Otherwise, who's going to run this place? The only thing I would say is the storage of materials here, paying is going to be, again, if we could have done this project 10 or 20 years earlier, paying what's going to be inflation-adjusted prices to store goods and material for every school. Is there any way that the other school buildings could take up any of that store space so that this thing where every school is, you know, thousands of dollars. Ken?

[Kenneth Lord]: The reason we get major deliveries here and store and deliver at the other schools, we don't have the space at the other schools. So that evolved because of the lack of storage space at the other buildings as they get. So we have to store. We might, you know, it's evolving. We need to limit the number of schools as we go. That's kind of why it's that bad.

[Luke Preisner]: Luke? All right, so fair work here. I'm going to try to make a motion, but I kind of want to explain and justify what's behind it. So, you know, I think through the ed plan, through all our hundreds of meetings over many months, we've got this like pretty perfect vision of what the school should be, and we're creating these efficiencies and proposing and voting on them. And, you know, all of us, all of these, if perhaps we can introduce a circuit breaker concept. So I think as we strive for perfection, we don't want it to become the enemy of a good ally in June or whenever we vote on this. So this motion kind of creates a circuit breaker. So a safety message. There's a lot we don't know. And we might get good news.

When someone was put on contract, provided updated costing and schedule information, we might get fake news. We're optimists. And so because at this moment in time, we don't have that information, I think that we should uh, apply kind of a troll to our steps, right? We're, we're going to go through these, uh, efficiencies and we're going to arrive at a final number and it's going to cost something and we won't know really until January. But if we have a skipper that trips it, the, uh, the debt service or debt exclusion, um, is quadruple what the recent override was. That triggers if the cost to finance this school is quadruple what the Prop 25 override generated on a manual basis then can we commit to pausing and referring the ed plan back to school committee so that school committee can decide what to change so that we get under quadrupling prop 2.5 override.

I'd like to make that motion.

[Unidentified]: I have a question.

[Suzanne Galusi]: Yeah. Is that like, that would set us back in the process, we would take back some steps. Yes. I mean, it would be much more expensive. We'd be saving money in the short term and construction costs could go up and up. Okay. Yes.

[Luke Preisner]: I say MSBA, you know, they give you a timeline, but most districts take their time through the process. And if you speak with MSBA, they'll encourage you to take whatever time you need so that the community is fully on board with the project. In the case of Lowell, I think There was a lot of community conversation about where to school. Now, a lot of these projects, they, um, you know, they'll construct a school in seven years. I think it took 13 or 14 years. And the reason it took so long was because one group of residents wanted to live in the, uh, the Belvedere. I don't know if you're familiar with the Belvedere neighborhood. And then another group wanted to keep it in downtown and it took them years to sort it out. And when they did, they came together. And Lowell's got a beautiful high school. It's right in downtown. It's gorgeous. It contains a historical thing and adds to it phenomenal new facilities.

[Member Jenny Graham]: Is there anything?

[Luke Preisner]: Ask a question.

[Member Jenny Graham]: If I can get into that delivery. Just ask your question. We have got to keep

[Andre Leroux]: So as a respect to our M&A team, so if we were to try to do anything like the motion that Luke just put forward when it comes to changing either the M&A plan, I know obviously MSB, we get pushed back with that. When it comes to changing, that would then impact the design that we're in the process of doing. So if we start and then halfway through something changes like that, because of the suggestion of the motion, how would that even impact the design more than just theoretical? I mean, we're in the process of building something. And then when you're changing, it happens process, but we don't necessarily have to. We weren't planning for it because it wasn't that came up. I mean, I can't imagine what it would look like.

[CAS00002491_SPEAKER_14]: I think because of the MSBA process, you would be kicked back to the very beginning of the process. You would likely have to start this process again. If you're telling the SBA that the Ed plans are starting from square one, I don't know if they would send you back, like really back or if you've seen further in the process. It will say the feasibility study agreement.

[Zoe Moutsos]: for 913 days, that brings us to August 2027.

[Suzanne Galusi]: That is the timeline we have. We have to have approval by the MSBA by that date if we're not going to them with a significant change.

[Member Jenny Graham]: Is there a second? Hearing none, we're going to move on. Matt, can you go to the recap slide for Santa Claus? There is a recommendation here on a, um, or into office. Is there a motion approved by Brian? Is there a second by Nicole? I will call the roll Jenny Graham. Yes. Mayor Lingo Kern.

[Kim Talbot]: No.

[Member Jenny Graham]: Dr. Gallouy? Yes. Marta Cabral? Yes. Ken Lord?

[Martine Dion]: Yes.

[Member Jenny Graham]: Jen Belanger?

[Martine Dion]: Yes.

[Member Jenny Graham]: Libby Brown? Yes. Maria Dorsey? Yes. Brian Hilliard? Yes. Tracy Keene? Yes. Paul Malone?

[Unidentified]: Yes.

[Member Jenny Graham]: Cole Morales? Yes. Liz Mullane? Yes. Erin Olapade? Yes. Luke Preissner? Absolutely. 12 in the affirmative, 0 negative. 13 in the affirmative, zero in the negative, one abstention. Negative. Negative. It was one no. Yes. Yes. 13 in the affirmative, zero in the negative, one no, one abstention.

[Luke Preisner]: Negative.

[Member Jenny Graham]: Negative.

[Luke Preisner]: Zero. No. Negative. Zero. No. It was a negative.

[Member Jenny Graham]: Oh, 13 in the affirmative. Sorry. Zero. Oh, one in the negative. Thank you. One absent. So 12 new affirmative, one in the negative, one absent, one abstention. The motion passes. Welcome Eric.

[Matt Rice]: So again, maybe up for Dr. Belucci to outline things here, but there were not efficiencies that were under part of the schematic design phase for the Welcome Center. There were several modifications that were made during the preferred schematic report phase. that reduced some office sizes, that consolidated some spaces already. So agencies were already reflected in the welcome centers themselves.

[Suzanne Galusi]: So just to, just to briefly, I know I've said this before, but just to, for people that are maybe just tuning in. So the welcome center, maybe AKA the registration center, We call it the Welcome Center. It is the hub of many public schools and we, even in this building, are very intentional about what we locate around our Welcome Center. So the families come here to register their children. They have immediate access to a variety of departments and they can get their questions answered or feel and receive some support. So the adjacencies that are critical to the welcome center. Our assistant superintendent for special education and student services Kim Quinn is located next to it. Our director of nursing Jen Silva is located directly next to it. Our director of English learners. Chelsea McNiff is directed, it's located right there. Our after-school program managing director, Katie Ossette is located adjacent, as well as our transportation major, Ina Williams, as well as MFN. So any question or any support that families need when they're coming here to start, that is located around the Welcome Center. Inside, are two very dedicated, very highly skilled registration specialists that interact with families coming in to register and the community.

Also within that space are some district translators. So they work directly with family that may need translation services while they are there at registration. One of our registry specialists is also speaks four languages, I believe. I'm happy to answer any questions about the Welcome Center, but it is number one core value for us that all those adjacencies remain as part of our Welcome Center.

[Kimberly Talbot]: Are there any questions?

[Kim Talbot]: Liz? Dr. Guzzi, I'm sorry, is the Welcome Center really exists right now in the high school? This is the minus four footage or bigger. How does this kind of compare?

[Suzanne Galusi]: Yes. When you walk in the front door in the foyer, right in front of you is the welcome center. And then I could grant you, but like all the offices that are kind of like being around it left to the right, even right behind this door, he is all English learner. Um, it was all needed right here. I, I think it's about the same. It might be a little, it might be, when you walk in the setup, there's not an immediate space for the registration specialists to like pull up to a table and work with families. They would have to go out in the hall or in the foyer where we set up some tables there.

That part is tricky. You walk in, there's kind of like a counter and then there are two decks. So there is need for kind of like, yeah, just a smaller like space where they can have sometimes potential conversations. Thank you.

[Matt Rice]: Yeah. We are doing some math here just to add things up. Rosemary is our educational planner that is listed. reminded me to note as well that some of the testing offices right now are actually in converted closets. That's the amount of space that people have. And so if there is an increase, and it looks like there's a really good opportunity of a little around 900, 300 square feet. So we're going from 4,700 square feet overall to 30 acres, but also right-sizing that for that space.

[Kimberly Talbot]: Any other questions?

[Suzanne Galusi]: When other school districts or most districts, this space exists within the central admin building, not like within our schools. It varies.

[Kim Talbot]: Okay, I'm just curious. To me, it seems like non-space, not the rooms. We can do that.

[Matt Rice]: I would say all central office space. It's not MSBA being like particular. Redford is just categorically non-reverb.

[Suzanne Galusi]: Yeah, I know this one just seems like particularly weird.

[Unidentified]: Okay, moving on.

[Member Jenny Graham]: Um, next is our remaining chapter 74 space that we previously looked at.

[Matt Rice]: All right, so this is a continuation of the last meeting, when we reviewed the majority of them, probably got through 75% of the space previously. So we'll go through the remaining programs. And these were the meetings that we had that went to the last SBC meeting. I will bring them to you at this point in time. And again, I'll just go through the reductions that are here, if I have any questions on any of the other talks or line it up after we get through it. So for programming web development, so that is Lisa's shop in particular, there was a determination of the related classrooms was not needed on top of the space itself, because the type of activities that are going on within job space are really conserve that for academic instruction as well as the creative programming and design piece that's involved there as well. That was an efficiency where we were able to find in programming and web development.

If I jump then down to film and TV. So again, this is one of the program spaces that increased in terms of size. It previously sat at 2,500 square feet, and it was sized appropriately for classes of, or counts of 20 students, grades 10 to 12, to be within that top space at one point in time. It also was the number of students that DESE allows for one instructor. There are two instructors currently within Philomente because all of those students that are potential in that program would be in the shop space at the same time or have potential. We needed to upsize the shop from accommodating 20 students up to 40 students. Again we have those instructors. This is not future planning. is accurately sizing the space that's a requirements.

Part of that but also to acknowledge the fact that similar to programs developed film and TV instructors felt comfortable by having a dedicated edited room because that's where footage really allows for two editing labs that would be distinct. And that's where footage also account for the the teaching of the recording studio as well as a control booth and associated storage spaces around it. It is a large number, but there's a lot of parts and individual space that are wrapped. And it's really right sized for the number of students to plan for that particular program moving forward. Let me just, I'll finish going through these and then I'm happy to swing back on any of them. So the next agency that was found was with arts in particular, the space. We had this discussion with some of the CTE programs during the last go around as well. And it's again trying to get an accurate understanding of how many students in grades 10 to 12 would be in the kitchen space at one point in time. And Culinary Arts is one of the AB programs that has students that do a week within the kitchen at Culinary Arts and potentially also outdoor in their hour space. So they're gonna have a different type of schedule And that allows for some efficiency found in terms of the number of students that would be in the kitchen at one point in time. So we're reducing from 5,625 to 4,219 square feet. That 4,219 square feet is still a 2,200 square foot increase from the kitchen that is currently located at Culinary Arts. That is one of the spaces that is the most vastly oversized of any of the CMT programs in the space right now. uh, and there's a space where students are, they're cooking, um, flames, their knives. There's things that we want to make sure that we have, um, adequate, uh, space around students and persons. Um, and that's really meeting the depth requirements still within that, um, reduced shortage that we have. And then the last set of efficiencies in this grouping of the chapter 74 spaces, um, is within dental async. Dental assisting is one of the new programs, and now the two that are not there yet that will be forthcoming. But we did have the ability to speak with some of the installers that actually do dental assisting shops really across the state. There's, I think, just one company that basically has installed them. They will give us some advice in terms of what other programs some sites are doing right now. And so there, the dedicated x-ray room, sterilization, square footages, um, that we had previously accounted in addition to the shop space can be, um, accounted for within that 1875 square foot shops. Um, it doesn't mean that those rooms go away or not. It just means that we're actually going to wrap them to the square footage of the shop.

Um, so overall, combining with the ad efficiencies, we have an overall net deduction of 900 square feet, 906 square feet, uh, for this, uh, for SODI programs.

[Member Jenny Graham]: Any questions about these space essences?

[Phil Santos]: The related classrooms in each of these programs, right? And so the difference between the main room and the related classroom, I assume, correct me if I'm wrong, is they spend most of their time in the shop room. Then sometimes there's the classrooms that they have to go through. And so they have to spend time in the related classroom. And so those aren't used all the time. I don't know what the percentage is between, you know, how they, but I'm sure it was looked at, right. Just maybe a, just to react, just the, the need for each of these programs to have related classrooms, because they're not all using them all together, right? You can probably program it in a way where alternately you can kind of have some more like shared rooms. And then, and then.

Maybe I guess I don't understand what the information support services stuff is, but that sounds similar to programming and web development. So the programming and web development got rid of their related classroom, because they can use their shop as that. Why couldn't information and support services also do the same thing?

[Matt Rice]: Great question. I'll take a stab at an answer, and I'm actually going to let Director Petlin chime in. Correct if I say anything incorrect. But generally what we found is that the breakdown of when shops felt like need a direct separate related versus not as when they're sort of a dirt shop, since they're actually getting chained and they're actually getting all sorts of things off as part of their actual CT room when they're in the shop. So the difference between programming and web development, which is more software based is that ISSN is not a very friendly, like name of opt-in to what people are doing, but it's more like networking is hardware. Um, in terms of actually like, you know, part computers, um, network devices and putting them back together. Um, so there is the ability for them to get to a sort of space if you will, in that separate relating, but we did have. That specific conversation with everyone of the 17 programs that we have here now to understand. whether we needed to keep a related room or we could sort of blend it into the shops. And it really came down to sort of the instructor as to what they felt was appropriate.

[Suzanne Galusi]: Any other questions about CTE spaces? I didn't know if Allen wanted to say anything. Chad?

[Chad Fallon]: Yes, can you hear me?

[Unidentified]: Yes.

[Chad Fallon]: Mr. Rice, you did a great job. It's almost like we went through all these meetings together. I will just say that, yes, what Matt said, there certainly are some programs that have decided they don't need an additional classroom because they feel like the space they have in their shop is adequate. But I just want everyone to remember that Related is a regulation of Chapter 74 that students have to have it. Our students have it in their academic schedule. So while it may seem that they're only used part, you know, in the morning of a school day, those classrooms are actually used throughout the day. Freshmen start their day, their experience in there, and sophomores, same thing in the afternoon. So the related room for those programs really does get used much more than just for some classroom time. So when we went through the efficiencies, we really had hard conversations about what this is going to look like in a new building with a bigger shop size that you might not need the dedicated related class. But I can tell you that I feel really confident after the conversations that we've built this right size now for the programs that really feel like they need that academic setting off the shop space. Hope that helps.

[Member Jenny Graham]: Thank you.

[Unidentified]: Are there any other questions, Lisa? Just about the toilet rooms in Culinary Arts and just sort of all of the lifting ones. Are those for the community that's coming to Durham or for the students with the program or both? And I guess that kind of applies to the toilet rooms that would be for their community-facing.

[Matt Rice]: Right. So when we've called out toilet rooms in any of the program, itemizations, the line items, right? It's because there is sort of an additional need for, this would be for high school students to be changing and have direct access to toilet facilities without going out into the rest of the building, because they may be dirty, like for culinary, it's more of a health issue, health code issue, versus like if you're in auto tech and you're just covered with grease or something like that.

In terms of toilet roof, or say the public, That would actually be included within the Bistro 489 square footage of 1,000 square feet. And then there's the other toilet rooms for general use for the entirety of this population. In some cases, again, for programs that students are not getting dirty, they certainly will have access to nearby toilet rooms, and they can go out and use those. I think the last iteration we did of these meetings, for instance, engineering expects to make a determination that Their students actually go out and use the Sydney toilet room, so we did take away those dedicated toilets.

[Unidentified]: Any other questions? Is there a motion? So moved by Dr. Lucey.

[Member Jenny Graham]: Seconded by Justice. I'll call the roll. Jenny Greene. Yes. Mayor Lungo-Koehn.

[Mayor Breanna Lungo-Koehn]: Yes.

[Member Jenny Graham]: Dr. Valutti. Yes. Marta Cabral. Yes. Ken Lord. Yes. Jen Bollinger. Yes. Libby Brown. Yes. Maria Dorsey.

[Bair]: Yes.

[Member Jenny Graham]: Brian Hilliard. Yes. Tracy Keene. Yes. Nicole Morell. Yes. Elaine. Yes. Harold Potting. Yes. Luke Frieser. Four affirmative, negative one absent. The motion is approved. Okay. are an extension of our central administration, their spaces that we wanted to make sure we covered.

[Matt Rice]: Right. So well, the first one is the teen health center that we, we know that we've talked about with this group previously but we haven't looked at efficiencies. I mean, we did the ability to have a dedicated programming meeting for the teen health center. after it was determined that it was included in the building. And what we were able to do is sit down and look at some prior examples and surrounding facilities where they did have shelters and make some evaluations about what was previously noted, we found an overall reduction of 255 square feet, which doesn't seem like a lot, but proportionally for the overall size of the space is consequential. And just to run through what those origins were, we had previously identified a need for two toilet rooms in, within the suite of teen health center. And I find that we could drop that down to a single toilet room. Um, consultation offices, um, were oversized. And so we reduced the size of them, um, as well as the quantity of them, uh, which resulted in overall net production error of 100 square feet. Um, there was previously a dedicated staff room. Um, and what we saw was that, um, there is a need for a small group council room, um, as part of a teen health, um, space. And so we can use sort of that small concert room and double the staff room in this multipurpose space. The dedicated room was removed. There is a mobile purpose room that added down below at a slightly smaller size. The storage space was reduced from 160 square feet. There were some other office spaces and support spaces that were added in. uh, to compensate, um, one educator office, um, which was part of this particular program, um, as well, the lab, uh, bed safety, you know, and in a soil that is those bottom three, which are required again by, uh, department rules. So we had an overall net production of 255 net square feet. Um, uh, image on the left-hand side again is for still in that, um, You see footprint, but we're up on the 3rd floor, which is also where the central offices, the welcome center center. At this point, we're located. We did have some discussions about the location for the health center as well. We want to make sure that it has to facilitate.

new members, teens visiting families, visiting needs be. And so it may have some benefit tip also go towards the nursing office for the high school as well, because there are opportunities for some shared resources and just having proximity of teens being able to go from that nurse's office into the teen call center where different services will be offered.

[Unidentified]: Questions? Their emotion. Motion to approve by react.

[Member Jenny Graham]: Second, let me call the roll. I am yes. Yes. Dr. Lucy. Yes. And Lord general answer.

[Mayor Breanna Lungo-Koehn]: Yes.

[Member Jenny Graham]: Libby Brown, yes. Maria Dorsey, yes. Brian Hilliard, yes. Tracy Keene, Paul Malone, yes. Nicole Moran, yes. Liz Mullane, yes. Arnold Potting, yes. Luke Prisner, yes. 13 in the affirmative, zero in the negative, one absent, one abstain.

[John Falco]: Jenny, do a second motion.

[Member Jenny Graham]: Sorry, Libby. And final piece of central admin, I think is the final piece.

[Matt Rice]: This isn't the high school administration's decision. Previously, I think really maybe the first time we actually had a session like this. We did the counseling spaces, so the guidance office and such that were associated with the school administration. This is really the remainder of the high school administration offices, including everything from the principal's office to the SRO's office, right, just to give you a sense of sort of what's included in this. Again, I'm just going to run through the revisions that were made.

general off waiting room with the toilet. So that description is the MSP items in terms of how they grab the space. We were increasing it from the baseline space that the MSP allocates under 98 square feet to 798 square feet. And that was to accommodate one additional administrative assistant. Um, sort of collected office area that is going to mix some more on the main office. There's another reduction down below. This is another dedicated office previously at 150 square feet. So even though that has increased the overall net production of the 50 square feet as we look at it.

We did remove also the teacher's mail and time room. Um, as the function could be accommodated for in the coffee room. This is a similar concept to what we did with a, an office. Um, I will back up a second and mentioned that, um, there's a fair amount of this administration space that it's reimbursable per the MSBA. It is directly out of the guidelines. I think above and beyond baseline guidelines, they also, um, indicated to us to be for the SRO office. as well as the campus security monitor office. So those are the reimbursable pieces and noted the non-reimbursable items here in the comments column as we go through. For instance, they reimburse only for two of the associate principal offices. We have four associate principals, those second two offices are non-reimbursable.

Jumped down all the way to the campus security monitor and the SRO office. We are putting those from 150 to 100 square feet with the campus security monitor because we're intending for that individual to be sort of on an island like they are when you walk through the door here today. They would actually be backed up to the main office, so they're going to be able to take some advantage of the efficiency of space working around them. And with the SRO office, it was more of an issue that, yes, more typically out and about within the school, as opposed to just sitting in their office all day long. That's part of their role and responsibility. So it didn't make sense to give them a larger office at the end of it.

[Member Jenny Graham]: Is there a second page, Matt?

[Matt Rice]: There is a second page. So I'm going to just go through these, and then we can sort out. The CT defection dedicated waiting space. This is removed in the understanding that we are a comprehensive high school, even though there is a A dedicated CTE reception waiting space A is remote and vestige of sort of the separate building that previously existed. So we're consolidating all of the administration space both CTE and academic high school in one space. So executive director office for instance which is still a part of the program will be located in the main high school administration. So again we just took away the dedicated separate reception.

The conference room was reduced in size given that both of the conference rooms will be located in a single suite and to make sense to have two of the same size. There was a need for a larger one that was in the high school administration office as per the SBA guidelines. And then a slightly smaller one here that still gives a good capacity. And then lastly, back to the phone booths, there were four that were identified here. Um, and there was, uh, there's, there's still a need for those private conversations, given that we have open office, high school administration, but reducing it from four to two. Um, so all those, uh, reductions, uh, were a total of 603 net square feet.

[John Falco]: Um, when we toured Arlington high school, I seem to remember the teacher face several One per floor per wing, I think. I mean, I obviously didn't bring any measuring tape, but are we saying 98 feet is all we're going to get for all of us across the whole building? Because, you know, we are going to have the cultural change if everybody doesn't get a classroom for themselves. Huntington went through that as well. That was less painful. because they're, in fact, frankly, lovely. This is featured in your own little kitchenette.

Oh, there are four more. Is this just a little number, Specky? You might shut up.

[Matt Rice]: To answer questions, there are additional teacher planning spaces that are programmed as part of a core academic-based authority that I reviewed previously. Honestly, I cannot tell you why the MSBA breaks it down like this, and they put this workroom down in Adden and then have the separate teacher planning spaces. I forget the names. But there's enough footage there to distribute across the entire medium of the building in terms of individual teacher planning spaces. Thank you.

[Luke Preisner]: So Matt, I want to ask about two things. So the school resource officer room and then also the graduate room. So with the school resource officer room, if you're making it smaller, do you think there's remaining capacity to add an SRO if in the future you find that you need additional SRO because you have this much more mixed population in the building? put a hundred square feet, accommodate two SROs. The manner you described, they need a place to potentially check email, drop off their things, and they're doing patrols, I guess is kind of how I was understanding your explanation. Is a hundred adequate for people to decide that you need another one because this population is far more mixed?

[Matt Rice]: So I can offer some thoughts, and I would probably defer to the school administration. I will say that for building is larger in terms of projected enrollment, say over at Seville High School, we had one SRO officer. For Waltham High School, where they're up at 1,830 students, they do. So I think the threshold in terms of when you might need to is probably a little higher than what we're programmed for at 1,385, just given precedence for surrounding communities.

From my personal perspective, I don't think that the mixing of vocational students and academic students would drive the need for an additional SRO officer. I just don't see that a typical consideration, but I'm not sure if I'm... I'm not asking to predict whether it would happen.

[Luke Preisner]: I'm asking whether capacity exists if learned that we need another one. Marta?

[Suzanne Galusi]: So currently right now, yes, the SRF might be extremely visible. And I would say that you really take those breaks in there. And it's out and about when it comes to passing time, when students are in class and lunch and so forth. They really just need a space to put their stuff away and a desk to check email and occasionally Canvas. So I'm not a school expert, but I don't think that they need 150 seats.

[Matt Rice]: So for two desks in 100 square feet, you could put two down there. It's not going to be spacious and comfy, but it all sounds like that's maybe not necessary in terms of the environment. It's really a place for them to sit down.

[Luke Preisner]: The second question I had was with the driver's ed room. Is the purpose of that room to conduct a driver's ed curriculum, or is that an office for something?

[Matt Rice]: in conversations about this earlier today. So again, to turn it over to Marta to.

[Suzanne Galusi]: Yes, so currently it is the place where they take phone calls, do registration. There's an office there and there's a person that is overseeing it, the teacher here at Medford High School.

[Luke Preisner]: Are they delivering a written or are they just processing applications?

[CAS00002491_SPEAKER_14]: I might ask Mr. Fallon if he's still on. because it's out of HIPAA.

[Chad Fallon]: Sorry, can you repeat that last part?

[Luke Preisner]: Is the purpose of the driver's education room inclusive of delivering driver's ed curriculum?

[Chad Fallon]: I honestly can't speak to driver's ed. I did mention to the team it's located within my office suite now but they have their own coordinator. And all I know from what I've heard from the coordinator is that the registry of motor vehicles requires that they have a space that's dedicated to them with a locking door and a phone.

[Member Jenny Graham]: Is that 150 square feet with other similar office spaces?

[Matt Rice]: Yeah, so it is an office space as opposed to a space where students are visiting, I believe. And they're not taking any sort of tests in there, if that were an option.

[Luke Preisner]: There's a driver's ed curriculum that every new driver in Massachusetts has to go through. And I'm trying to learn what the purpose of this is. So far, I haven't really heard, I think, a full, characterization of what goes on in there. I just heard it's a room that can be locked and it's got a desk. But I know there's a need for driver's ed every year. Half the students are probably getting student permits or or maybe not half maybe a quarter will be seeking permits any given year.

And 150 square feet. I mean given how generous we are with the other rooms doesn't seem like a lot if the purpose is to deliver a curriculum.

[Chad Fallon]: That's so member Graham, if I can, the classrooms that are used for the parent classes and the student classroom hours are just high school classrooms that are used after hours. The office is specifically for the drivers and staff. to have a locking file cabinet and a desk with a phone. No students are meeting in there with the coordinator. It's just for their space.

[Luke Preisner]: Oh, OK. So it's office space for the people that are conducting the program.

[Chad Fallon]: Yes. No student goes in the space. It's just for the adults.

[Suzanne Galusi]: And there are only two staff members.

[Chad Fallon]: Yep. We have a coordinator and then a classroom instructor.

[Luke Preisner]: And they share 150 feet.

[Chad Fallon]: Yes. They're never in there at the same time.

[Member Jenny Graham]: Thank you. Are there other questions about these spaces? Is there a motion? Moved by Dr. Galuzzi.

[Mayor Breanna Lungo-Koehn]: Second.

[Member Jenny Graham]: Seconded by Brian. All in the roll. Jenny Graham. Yes. Mayor Wendell Kern.

[Mayor Breanna Lungo-Koehn]: Yes.

[Member Jenny Graham]: Yes. Yes. Yes. Yes. Yes. Yes. Yes. Yes. So Matt's going to take us a quick recap of where we are.

[Matt Rice]: So this is the conclusion of our space efficiency exercise. And so the sum total of all the recommended efficiency from this evening with gross square footage. And again, the gross square footage is one and a half times the net square footage we have. So it's something for hallways and walls. stairs or that percentage of space. So that's how we get from the sum total of the net square footage to the gross. We were previously at 570,186 gross square feet. As of this evening, as we conclude the process, we are now down to 570,186 gross square feet.

And again, doing estimated total cost reduction as well associated with that gross footage. We're now down to a current snapshot of our budget estimate at $746,153,410. Correct. We have another slide coming up that wraps in Ken's world. This is exclusively just the square footage reductions that we have and sort of is snapshot of where we are on square footage as well as the estimated total project cost. Down below is again that listing of spaces that currently and features that are currently included in that total project cost.

What we have after that as well is a slightly different way of just going back and looking at all the different that have occurred since the PSR session, that last submission to the state referred schematic report submission. At each one of the meetings, 25, 910, 922, and this evening, indicating that that drop was in terms of square footage. So we started out at XO8, 792 gross square feet, and we're now down to 567, 877. It's almost 40,000 square feet.

Um, but over that, that we pulled out, um, again, without affecting the educated plan. Uh, and the MSBA has confirmed for us, even again, most recently that, um, need to be respecting the educational plan. They will be reviewing that as we said, the schematic design package. Um, but the fact we have these adjustments in the very, um, granular way that we've been talking about it with every single educator we've been going through and we've been remaining through to the case plan. Um, I believe that that the, um, supported and welcomed by the MSBA, uh, as sort of an effort, uh, efficiency effort that we have gone through, um, in terms of the dollar values of what presents, um, close to $5 million in terms of estimated savings, just based on the reduction in terms of, um, again, gross square footage program size within the building. Um, so, uh, very consequential to the overall budget as well.

[Member Jessica Parks]: Matt. Give him one second.

[Matt Rice]: Yeah, so this is a good slide as well. So this is what Ken spoiled. Basically, it makes our number that we had gotten both in terms of square footage that doesn't change, but the total project cost. And it also accounts for the credit associated with each system recommendation that was accepted. Um, as well as the additional cost to support, um, the power purchase agreement up front. And so when those 2 things are accounted for at the cost, and remember, I talked about the 42 multiplier and the 22% multiplier. We put all together, we're now just shy of 700Billion. Um, it feels much better than saying $699M of the project, but that is incredibly considerate. I mean, we're making $100M out of the project.

very thoughtful discussions, well difficult considerations from the MEP systems as well as the overall space. So that is the result of a tremendous amount of work already here in this room, as well as the entirety of the user team educators that have spoken over the course of the past three months, four months going through this process, as well as the advisor teams as well. So a lot of appreciation to all to get us to where we are at point.

[Unidentified]: Question.

[Member Jenny Graham]: Okay, we're going to move on to the next section. which is to take a look at some parking alternates for parking and athletic fields. So if you remember, we're preparing potential alternates for parking and athletic fields, and we have decisions to make on that tonight. And we will end this meeting, I promise, by talking about any other proposals, comments, space efficiencies, et cetera.

[Matt Rice]: We do have a goal to share in terms of updating the site plan here, but I want to take us back to the considerations that we're looking at during both the preliminary design program phase, as well as the bird schematic phase. We're looking at various options that we're placing a field over the top of parking, either in a multi-story parking situation, or just a single go parking really at grade with a structured field above. You can see here that each of these options came with a very significant price tag associated with it. It also came with the necessary compromising of the opportunity for total pay extra panels to be placed over that parking because we can't put PV panels over parking if we haven't pulled over parking. It's just those two things don't work.

Because of this, we are recommending that we abandon all of the field over parking options because we have already decided to go down that road of aiming for 100% net-zero energy, for which we need to have those solar canopies or the parking spaces. So it's really prioritization of sustainability of the project versus additional field resources. These would have been field inventory to the site. I mean, that's the main advantage that they offer, but in terms of other options, that is the recommendation. We eliminate all of these field or parking options.

[Member Jenny Graham]: Are there any questions?

[Mayor Breanna Lungo-Koehn]: To the chair, member Graham. Yes, I'll move that motion to eliminate all these options as one who's very concerned about not only the debt exclusion passing on June 8th, but also just how this will affect a number of our residents who may not be able to afford something so high. I'll say that I'm very happy that we've been able to reduce somewhat from the original price tag. I just fear that it's may not be enough. So although I didn't second Luke's motion, I do think that as we're designing and as we're knocking on doors and trying to get support for this project, if we feel that we need to reduce it more down the line, I think that needs to be still on the table somehow, some way. Thank you.

[Member Jenny Graham]: On the motion to remove from consideration, is there a second? Second. Any other questions? OK, I'll call the roll. Jenny Graham? Yes. Ramon Go Kern?

[Mayor Breanna Lungo-Koehn]: Yes.

[Member Jenny Graham]: Dr. Galusi? Yes. Marta Cabral? Yes. Ken Lord? Yes. Jen Belanger?

[Martine Dion]: Yes.

[Member Jenny Graham]: Libby Brown? Yes. Maria Garcia? Yes. Brian Hilliard? Yes. Tracy King? Paul Malone. Yes. Nicole Morell. Yes. Liz Mullane. Yes. Erin Olapade. Yes. Sue Preissner. Yes. 14 affirmative, zero in the negative, one absent. Those items are removed. Okay. As we round the bend here, as we have been discussing, back in April, we tabled hundreds of sufficiency proposals for a later date. And today is that later date. Um, so what is attached to the agenda are those items for which they have not been otherwise accepted or integrated into the project. Um, in some cases, uh, things that were partially accepted.

Here's how we're going to operate through this next section. We're going to go very much like we have, as we have talked about these spaces. Um, and. The first thing that I'll ask the committee is if there are motions to untable particular items, I will ask you to use the number on the chart to do so. If there is a second for unsealing, then we will deliberate. We'll welcome public comment about those items on the table, and then we will vote. We'll move through category by category. And then at the end, we will ask if there are any additions from the public, from folks who have been here with us all evening. Thank you very much for your patience before we officially close the book on space issues. Are you okay with that?

[Luke Preisner]: Can I ask a question? Luke. I just want to confirm that because I made the motions and the way the tabling was accomplished, Um, that prohibited from untabling anything.

[Member Jenny Graham]: No, no, you're able to untable things.

[Luke Preisner]: The April 27 was, um, uh, it's, uh, I, I think, uh, uh, me from doing anything. Um, we should take a look at it.

[Member Jenny Graham]: That was for, that was during that, those were rules that were adopted for the for the course of that meeting, you are welcome to untable the thing if there is a second and a majority vote.

[CAS00002491_SPEAKER_14]: Okay? I just want to make sure I understand. So we can even choose to untable things and vote, et cetera. If it doesn't remain untabled, or we don't make a motion about them?

[Member Jenny Graham]: They will permanently stay on the table. This is the last meeting where we are making these changes.

[CAS00002491_SPEAKER_14]: So they vote with the table, get untable. Correct. Okay. Thank you.

[Suzanne Galusi]: Nicole, two things. So we don't have a motion to do this, so that we can stay on the table in front of the committee.

[Member Jenny Graham]: Yeah, we can dispose of them at the end of this motion.

[Suzanne Galusi]: OK. And just for a discussion point, I was looking at this as we're going through this and before, and a lot of these were addressed through other votes, not specifically for these motions, but through all of these speeches that they did. know that the vast majority have been, not these specifically, but a lot of the prevention and then have been voted on in Zoning Priority.

[Luke Preisner]: The 29 that have been, I think those.

[Suzanne Galusi]: For sure. And those are listed there, but I was saying majority. OK, so we'll give this a spin. The first category is administration and guidance.

[Member Jenny Graham]: So what Matt is going to do to anchor us is make sure that there's an understanding of what those spaces are. So if people have questions, there's an anchor there. So Matt's going to find the slides and pull them up for administrative guidance. Are there any motions to enable any of these changes for administrative guidance? Hearing and seeing none, I'm going to move on to the next item, art and music. Matt, if you can pull up the art and music section.

[Unidentified]: Will? Just on the council one, the staff's class for 950.

[SPEAKER_30]: For administration and guidance? Yes.

[Unidentified]: That matter with the other classroom reduction, it should get reduced down to the 900 as well.

[Member Jenny Graham]: There are a motion to reduce the steps classroom by five square feet. By Aaron. Seconded by Liz. Sorry, that would be a motion to unable. Unable. Aaron, Liz, I'll call the roll. Jenny Graham, yes. Mayor Lundquist. Yes. Yes. Yes. Yes. Yes. Yes.

[CAS00002491_SPEAKER_14]: Yes.

[Member Jenny Graham]: Yes. Yes. Yes. Motion to reduce that item by 50 square feet. Motion to reduce. Seconded by Liz. With me, guys. We're going to get there.

[Luke Preisner]: Motion to reduce it further to 825, which would be the minimum. Although I don't think it's a reimbursable space. Proposed an amendment to 825.

[Member Jenny Graham]: Is that an amendment you'd like to accept?

[Andre Leroux]: Can you just Will you just clarify as to why you want to do that?

[Luke Preisner]: Sure. So MSBA, this is not, I don't think it's an MSBA reimbursable, but if it were, MSBA has two endpoints, low and high. The maximum reimbursement is for 950 and all our classrooms were sized until we dropped it to 900. The minimum is 825. So I'm just offering an amendment to further reduce space because we're paying probably over a thousand dollars per square foot.

[Member Jenny Graham]: Is that an amendment you want to accept?

[Andre Leroux]: Well, I just calculated what the steps actually like what services it provides. If reducing it under the 900, what we've been doing with all the other general classrooms, what that would look like.

[Kim Talbot]: So the steps program and steps classrooms that have been out for an extended period of time that are returning to school after a holidation or another long absence need support. Can I ask a clarification question? Sure. How many students can 825 therapy accommodate comfortably?

[Matt Rice]: The typical classroom size at the lower end would be 23 students if they were sitting in a general academic setting. I think this program, even though it's not technically special education or is it? but you are working with smaller groups of students and they're maybe typically around the 15 range as a target size. We'll say we're trying to keep this at the typical classroom module to match in the rest of the school so that it fits into the program and the structural module of the building itself. Whereas trying to reduce this one versus all the classrooms to that lower eight to five would sort of complicate how it integrates in with the rest of the thing.

[Kim Talbot]: And the number of students in that space at a time is variable and can change to week, month, month. I'll have teachers in the current model that provide support to students. There can be at times more than one adult in that space boarding students, also students with a full spectrum of students that are returning to school, that I would argue require more space than a typical classroom while they're at the school.

[Member Jenny Graham]: Did you hear, Hannah? Yeah, I think you encompassed it well.

[Suzanne Galusi]: I also wanted to add that your students that are in there for the full internity of the day and you're all in that space. being able to set up the space at different times would be helpful for students to be able to access the content areas throughout the day.

[Phil Santos]: Phil? I got a design question, I guess. So when we have these numbers, right, at the end of the day, are you required to meet those exactly? Are you going to show, or is it a minimum, You know, because the way you talked sounded like if we go to 825, it's going to make it harder to design something to accommodate. But if you give it, if we say when you give nine, is that a big deal at the end of the day, you know, where it fits structurally to your thing? Because I assume you're not going to be hitting all these numbers.

[Matt Rice]: Right. I wish there was like a very, I guess, no answer to that question. So the way that the MSBA works is that At either end of the range, 825 of the 950 break 25 and we produce something that is like eight or four square feet called on it. We get asked to go back and design it and get an 825. If we are at 950 and we go to 951, we get the same feedback. At 900, uh, where tip of glass rises, we are allowed fluctuations above and below with a certain percentage. And that is fine and acceptable.

[Phil Santos]: If, like, we give you the minimum of 25, but it just fits to give 900, like the comment, well, we're not going to just, like, you know, add structural beams and make this thing, you know, awkwardly. We're going to give it a 900 square foot room.

[Luke Preisner]: And to Kevin, the need for space, is 915 a more appropriate size for your needs?

[Kim Talbot]: I think the more standard side from comparable what. The other sides. I'm going to be in the program. But I'm going to.

[Unidentified]: With her on my.

[Member Jenny Graham]: So program. 900 square feet. I will call the roll Jenny Graham, yes, mayor Lundell current. Doctor yeah, I think about him or yes.

[CAS00002491_SPEAKER_14]: Yes.

[Member Jenny Graham]: Libby Brown. Yes. Maria Dorsey. Yes. Brian Hilliard. Tracy Keene. Paul Malone.

[Nick Giurleo]: Yes.

[Member Jenny Graham]: Nicole Morell. Yes. Liz Payne. Yes. Eric Cuddy.

[Unidentified]: Yes. Lou Kreisner. Yes.

[Member Jenny Graham]: 13 affirmative, zero in the negative, two absent. That stays reduced to 100. OK. Um, as we are going through these topics, if there are folks who are hearing motions that they would like to speak on, if you could either raise your hand, you're on zoom or come sit in the public participation chair, that would help me know that there is somebody who wants to speak on the same that people are talking about. Okay. Art and music. Are there any motions on table? Any items?

Hearing none, I'm going to move on. I also have a question.

[CAS00002491_SPEAKER_14]: When they say yes, we've already accepted it. We make other space changes. Correct. Correct.

[Matt Rice]: If it's a straight, yeah, that exact original proposal was reflected. And if it was a yes with modifications, there's additional text description in the council as to how it would modify the proposal.

[Member Jenny Graham]: Try to filter out all the yeses for the purposes of this document. You all received the full document in your email last week. Yes. Yes, it is. No, no. If you're looking at Jada, this is the same. The posted agenda includes only those items that are still unadded. Item number four is auditorium and drama. Are there any motions to untable? Hearing none, we're going to move on to item number five, is our chapter 70 programs. Are there any motions to untable chapter 74 items?

Hearing none, we're going to move on to item six, which is core academic spaces. Obviously, there are several sides of our agenda space. Hearing none, we will move on to dining and food service. Are there motions to untable any item in dining and food service? Hearing and seeing none, I'll move on to item number eight, which is the media center. Any motions to untangle any items associated with the media center? Hearing and seeing none, we'll move along. Item number nine, is the medical suite, so are there any motions to untable items in the medical suite?

Okay, hearing and seeing none, we're gonna move on to item number 10, which is non-Chapter 74 programmed labs. Are there any motions to table any items associated with Chapter 74 labs. Hearing and seeing none. Are there any item number 11 is other and are there any motions to untable any data listed as other. Hearing and seeing none, item number 12 is special education. Are there any motions to untable any special education items?

[Luke Preisner]: I do want to say something. I'm not going to untable any of these because it's nine o'clock and it's not hard to forecast how the duration would go. I do want to ask people to kind of reflect a little bit. The last override passed narrowly, and it generated $7 million, an additional $7 million a year for those. I think everyone in the community, or at least everyone that I know, loves the school system. They support education and, you know, to the extent they can afford it, we will certainly expand the services that, yes, our children. We love our children. We love our neighbors' kids.

I think most of our parents know many kids in the school system. So collectively, we voted yes for that override for $7 million. It was, I think, actually $7.5 million. Everybody knows what the personal costs that will derive to them. You know, what I experienced is not different than what Aaron did, but we both know what we experienced. We reflect on how many multiples of that our community can bear. And, you know, earlier I kind of unsuccessfully tried to make a motion put in the circuit breaker and I'm not going to that motion. I was probably prevented, but, um, if the annual or really the stabilized annual debt service, um, if it quadruple seven half million, so numbers 30 million, if it's simple, um, then, you know, we should probably take a moment. Not to go back to square one with yet plan. but to revise it just like we did in June.

Because I think as we refine our vision and really try to protect this facility, it's possible that in the course of all that knife fighting, largely to me, we'll see a good outcome for our kids. And the reason why I want to reflect, because I don't want to lose that outcome. So, um, uh, quadrupling that overnight, uh, means something and I won't get into the math, but I made some pretty reasonable assumptions about the things that matter. So our rates and SBA and, you know, quadruple that override gets you into a total project cusp. That's sort of in the neighborhood of what we're talking about.

to get into more specifics, because the CM is going to have a big voice. They're going to tell you what they have to cost. And I'm going to expect that $699 to change. I can't tell you which direct it's going to go. But I hope that we don't lose sight of a good outcome for everyone. So that's all I wanted to say.

[Member Jenny Graham]: Are there any members of the public that would like to speak? I need you to come sit right next to Dr. Hluby, so that everyone can hear you. Will you please provide your name and address for the record? And you have two minutes.

[Bair]: I'm in the mind of looking. Your name is? Oh, I'm sorry. My name is Tiffany Bear. I live in West Bedford. Thank you. Many people I know won't vote this, because it's just 6% if it goes. I mean, these are wishful thinking, I think. The conference rooms that could be shared, like with the MFA and the Kids Corner, but the conference room middle, they can share it. You do scheduling. It can work. A lot of these sizes of things, it's just like fantasy, meaning it's like the optimal of what you want. But in real world, you need to bring in some. Because we can't afford to have our taxes go up another two grand or whatever the heck it's going to come out to be. It's just not doable. People who are actually funding the project.

I just think there are cuts that can be made. And you guys are bringing that pitch. Like, oh, no, I want this all for myself. And I think it's great. And it's going to be perfect. But the world isn't perfect, and money doesn't grow on trees. So you've got to be cognizant of that. And I don't think really you guys are. This is my first meeting here. I know I respect what you're doing and all, but it's a lot. It's a lot. And there's a lot of people saying, oh, hell no. I'm not going to vote for that. We know our school, this school is run down in a jump, for the most part, by Darwin here. Things falling from the ceiling, heaters not working, that sort of thing. But to go to the pool stream and have all the fantasies in one bucket, and oh, the community is going to pay for it. It's going to happen. It is going to happen. Got to bring it back a little bit.

Thank you.

[Kim Talbot]: So I'm going to leave them today.

[SPEAKER_20]: I just have a question and it's not in the building. Back in the spring about the road. And so when I'll talk in my neighborhood, we're on Winford Way. And there's like the bells, I don't know if anyone's been with it or not, the bells behind us, walking paths, jog paths, people running their time, riding bicycles. So the talk is now that they're gonna put the S road find our homes. This is going to be not that wild. It'll be fun. Um, that is not true. Oh, okay. That continues to not be true. Okay. So like you said, it just was brought up again in the neighborhood. So everyone's going to get in. So we just needed to have an answer with that.

[Member Jenny Graham]: But, um, no, there is an active ongoing discussion about emergency access to this site because as you all can see, The one minute and one minute is a concern that we are working through. There's no answers to that yet. But to the question that you are specifically asking about coming through with Brooke, that is not on the table. And it never was, because it wasn't viable. It was not viable at the very beginning, and that has not changed.

[SPEAKER_20]: So it's like, whenever they disagree with that second one, we'll be- The others will be the first to know. OK.

[Member Jenny Graham]: Yeah, thank you. I promise. I live here. Thank you.

[Andre Leroux]: Hi, everybody. Nick Liggs, C2 Tainter Street. I know it's late. I'm going to slow this down a little bit. I have three kids that are going to attend this school. The other two are going to go here for the entirety of their high school experience. So to be clear, I strongly support the project. and the current design, including all of the non-core programming that was discussed throughout numerous meetings over the past few months. I also want to make it clear, though, that I have compromised on space costs. Over the meetings for the past several months, I have very happily seen the committee and the project team do the incredibly hard work of reviewing design line by line, meeting with educators dozens of times, and getting their input on what's facing what they know.

all to risk in the really, I think, remarkable cost reduction scene here. So I actually think you're shortchanging yourself. So in April, for the first round of cuts made before the PSR was submitted, the estimate for C2.28 was $850 million. So to now be below $700 million in estimated costs is actually more eye-popping than the figure you gave. So give yourself a little credit, I think. Before that meeting ended, Um, there was a large slate of cuts are now on the agenda. Um, that if enacted resulted in, according to the calculations of that meeting, but 219 million, um, many of them were judged to the educational, but what we have now after all the process is, uh, cool. That is below $700 million that has preserved all non-core programming meets the ed plan. It ensures that MF and LEAP and Kids Corner have a home and will continue to have a home. It preserves the pool, which is so important to so many public commenters in the process. It preserves all those alternative pieces that we would have lost if we built a gym new. Expands athletic facilities with a track and a football field. And it does all of this while still lowering proposed square footage by, I can't remember the exact number, but a lot. And if that isn't a compromise we're celebrating, I don't know what is. So this is a saving of over $100 That broad slate of cuts was 200. That's meeting halfway. I don't think you could come up with a more perfect illustration of compromise now. We're now within 10 percent of the existing high school square footage. After MSBA reintroduced in my opinion this is not like a check figure in my opinion it's highly likely that this design is going to get us to a price that's lower than the code upgrade was which as everyone remembers was the bare bones doesn't meet the plan do as little as we possibly can. costs that would have preserved this building, we are quite likely to come in lower than that. That's incredible to have all of this new space, this new program, come in cheaper than that option.

Now I'll wrap it up. So in a democratic process, it's very rare to every single thing that you've asked for. I've seen spaces get cut that I would have preferred to stay, but that's OK. I will still be able to support the voting yes to that exclusion. My hope is that everyone on both sides of this issue, people who want to see rooms restored or who want to see more rooms cut, can meet in the poll and say, despite it not being correct, despite it not satisfying every wish that I have for what it be, I can support it. I can vote yes on a debt exclusion because in the end, the kids in the educators community have a much greater need than my, you know, my desire to be right about how the school is designed. I hope everyone is able to see that. So thank you very much for all your hard work. I'll see you next time.

[Unidentified]: Thank you.

[SPEAKER_26]: Hi, my name is Terri. I grew up in Manfred. I went to Manfred High School. I have two children, I have not lived, I've only lived in Medford, back in Medford for the last 23 years with children. I lived in another town, I took children to Medford for Catholic school, which was a choice my husband really wanted, and I was willing to do that. I do think that the high school need to be addressed, obviously. I support the children. I hate to hear when people talk to say it's whether or not I support the children, and you don't support children. I do support children. I don't have unlimited funds. It took me a long time to be able to afford my house here. I don't own my house out here. I can't leave to go somewhere else where this overrun might not be an issue for me because, you know, truth be told, I have very low interest rates because of COVID. That being said, this is my first meeting here. I wish there were more people who would give or take a little bit more instead of, I get it. You want the perfect? Everybody can't have perfect. It's not possible. And the cost that this is going to be where it's very unknown.

I'm retired from a full-time job serving the community in a nonprofit. And I am now working a part-time job as my taxes continue to climb. And I realize that's because my house and my value of my house has gone up. you know, for anything, that's just crazy. But, um, I'm just saying it has to be affordable, affordable. I supported paying. I paid my taxes when my children didn't use any of the public services for schooling. I never bought that. Now I'm here. My kids are older. I've educated them. I've done what was necessary. And I'm thinking I'm going to have to leave my home because we want what we actually truly need. I get it. I get everyone wants what they want. It is kind of disappointing. It's clear just from somebody who's never been there before and who is not on social media, but I do talk to people in the community, it is clear that there are really factions that just don't have any willingness to maybe consider something else. And that's really disappointing. It didn't take me more than 10 minutes to figure out which side people were on and which people were going to put up motions, which people were going to second, or even want to hear something different ever. It's kind of disappointing. But I do support the children in this community. I support the people in this community. I worked a nonprofit in this community 35 years. I didn't make a whole ton of money, but I did my job here, and I am proud of the fact that even though I didn't make a lot of money, I support the people that are around me. I support new high school. I do not support some of the costs that seem to be outrageous. And I get it. Construction is not the price. But you know what? I waited 17 years after I bought my house to be able to have a 1960s kitchen that had structural issues until I could afford it. And I didn't get everything that I wanted.

So I, you know, I get that everybody would like a few more feet, a few more feet here, a better place, a better whatever. I get all of that. But it's disappointing not to consider the people that are going to pay for that. And in this community, it seems like If we could only move the elderly, I hope things would be better.

[Member Jenny Graham]: Nobody feels that way. I'm going to remind you that I asked everyone to keep their comments to two minutes. That's fine. That's all I'm going to say.

[SPEAKER_26]: I support the community. I support a new school. I don't support knowing anything else that it's going to cost.

[Member Jenny Graham]: It's a really fair point, and I will address that at the end of the meeting. Thank you. Thank you. name and address for the record.

[Nick Giurleo]: Good evening, everyone. My name is Nick Jorleo and I'm part of the Robinson room. I went to the school. I've said before, all of you that I consider much of my success in life due to the great education I had here. So I feel passionate about what this committee has been doing. I've been trying to attend all meetings and I take vigorous notes as I sit here. I have to say that I share the member prisoner in terms of considering our costs. Again, we all want the best school possible, but we have to think about affordability. We have to be realistic. Just sitting here tonight at other meetings, it just seems like this committee has not been doing enough to address that in terms of making reasonable reductions to square footage to try to eliminate more than we need for our vision. I'm hearing, hey, we're adding square footage, but it's the last thing we should be doing. I'm hearing tonight, arguments, keeping conference spaces, you know, grand schemings, is that real? They need to be bigger. It just seems like there's not enough compromise going on in this committee. It just seems like not really, we're seeing really, you know, discussion, people are really thinking about these issues. And the end of the day, the number one thing everybody here has to think about is how do we get the voters to approve this? They're concerned about the tax impact. just extraordinary cost of this project, regardless of reductions that occurred to date. This is something we have to think about. At the end of the day, every year has got to be focused on the prize, which is getting this passed, getting a new build. I was thinking just really the past few weeks, the issues with infrastructure here, that power bridge, the sewage issue, obviously things need fixed here, but at the same time, we've got to be realistic. It just doesn't seem like we're there.

as well as what they're doing right. So thank you.

[Member Jenny Graham]: Thank you.

[Suzanne Galusi]: Hello, my name is Erin. I live on Rothery in Medford. I have two young children, three and five. My five year old just started kindergarten. And I've been so energized by the process of Building a new school, I mean, it's a once in a lifetime opportunity to create a school that's not just for the now, but also for the future. And by the future, I don't mean my kids. I mean, maybe my kids' kids. I mean, maybe, how long has this school been? How long ago was this school built? 1970, that's 50 years, right? So we're looking at 50 years of school, and the updated building capability now, it's five years longer. So that's what I carry in these conversations. I've been in tech, I work for e-commerce, and there's this fallacy that we have in the e-commerce of like a short-term gain versus long-term loss. And so that's something that I take in for this, and I absolutely hear the concerns of affordability, because in this economy, what else can you do? But what I've also seen is a company that has had these really thoughtful discussions and cut $150 million from the first estimate, which to me speaks volumes. So I guess I stand in a place that I want the community to feel heard, who are worried about affordability. Also, I want to go back to another earlier point, that we are now at a point that the cost of building this new fantastic high school is the same as it used to be. We've reached, we've converged on that point. We're just fixing what's broken is the same cost of building this new fantastic compromise across both sides. And so I just wanted to thank you all for your hard work on getting back $150 million and still keeping you along tonight. And thank you in advance for my kids a couple of years from now when they go here.

[Unidentified]: Thank you.

[Ada Gunning]: Next. Hi, I'm Anna Dunning. I live at 49th Avenue. I have two kids in elementary school up in the Glen. And listening to this meeting and previous meetings, I feel like we're telling the tale of a city that has squeezed public resources and real estate such that we now need this high school to essentially provide the community with all these resources that we have nowhere else to put them. Like kids corner, administrative offices, et cetera. And this group of people here, you guys have been putting in so much time and effort to working through efficiencies, making it affordable, listening to the community, but really what you're building is more than just a high school. You're kind of compensating for, it feels like a generation of not providing these resources or not allowing places to have, throughout the community.

And it's tough because now we're at a point where it's at maximum cost and the affordability concerns are very, real, but at the same time, we cannot just take the can down any further. So, um, I am connected with a lot of young families and people are really psyched about this project. They're really excited to get out there, go door to door, talk to people about this, vote for this. Sometimes the loudest voices you see online are not representative of the quiet majority of people in town. Um, so there's a lot of excitement out there. And I want to bring to the committee the work that you're putting into this. People are watching, people are really eager to see this project to fruition. So thank you. Thank you.

[Rebecca Davidson]: Can I address for the record? Yeah, my name is Ellen Ruffin. I'm at 52 Stickney Road. I just wanted to say thank you to you all. I was in a long, boring meeting, and I know you guys have it a lot. I actually do see a lot of evidence in the slides, in the numbers of square feet of the dollar amount, because under $700 million now, that people are working really hard to compromise on things. And I think we see part of that in these meetings. But there's a ton of work that's going on behind the scenes. Not only that, but the number of meetings that Dr. Kaluugi has been having with directors of different areas.

I feel that I'm really grateful for all that. I think you reject the thought. I was having a conversation with someone the other day. I don't really know anything about education or construction. And the number that people want is amorphous. not in just throughout like 699 sounds better than whatever we were at says, but I know it's for that. So I see the compromise. I appreciate the compromises. I think this is something that our community support and I look forward to working on that. So thanks. Thank you.

[Andre Leroux]: I was at the meeting as well, saw the $8.5 million donor, and see the work that went into doing this, to see all the different, all the different contracts were completed, and with the remaining time, and I, when I talked to my friends, kids that have maybe moved to the city recently, or just have kids in the city that they, So I'm really excited to give this new nation to those, to those families and say, this is, this is where we are, this is what we get to know, and this is what our kids get to have. My son goes to this corner here, great, great community.

[Unidentified]: Thank you. I do not have any children, so all children are to care about equally. Part of this that I wanted to see most is the part that I missed.

[Suzanne Galusi]: My thing is indoor air quality, so I'm very interested in HVAC, and I don't really know when is the time to proceed, so I just want to say that you have to shout and anyway to say Boston, at least think about future-proofing so that, you know, you're able to upgrade systems 20, 30 years from now to whatever is standard, 23 to 30 years from now. There are indoor air quality standards, really, but globally, we're working very hard on that.

And so I think there should be a demand-controlled ventilation. There should be CO2 monitors everywhere. CO2 monitors should be room by room, whether it's a conference room or a classroom, and that should dictate

[SPEAKER_26]: how much ventilation you have. Probably heating and cooling should be separate from your ventilation so that it can work well.

[Suzanne Galusi]: There should be heavy use of ERVs. There should be measurement in your PM 2.5 and outdoor. That ray should be used continuously to monitor how well your filters are working. That can save you money because you probably don't have to change your filters nearly as often

[SPEAKER_26]: as a timeline. Instead you're getting this continuous data. There should be a dashboard that everyone in the community can look at.

[Unidentified]: Like you can look at the public school system because they are doing some of that. Thank you. Thank you. For the folks on Zoom, we will

[Member Jenny Graham]: being to you and just when I was trying to help the people who have been standing in line for a bit be able to down.

[Member Jessica Parks]: First off, thank you for all of the hard work. I know and all of your voices have been incredibly valuable as part of this process. I have just a few questions, I guess. Can we have a matter of the cost bringing this to code? Because I guess my point is, I get it. This number can be scary to a lot of people who aren't in this field. And when we think about this number, we're thinking about the 699. And then once we have the cost to bring a code, it's what are we companion to? And what are we going to do for it? And what do we estimate we might be reimbursed? I know we don't have an actual number. We won't have an actual number until next year, but could we estimate 200 million or more or less? I mean, is it something of that? And then also thinking about, I've heard a lot of people say, we don't know what the number is yet.

Projects I've seen get to the stage and increase directly.

[Matt Rice]: I don't have those particular metrics. And I would even advise against trying to say, well, it's going to go up or it's going to go down. Because the only thing that we know right now is that we know which way we're going to go. We know that we're hitting in that zone. It's the target that we're aiming for at this point, given all the scope that we have. But there are some different variables that are coming into play with the construct manager coming in, but also having the ability to get to a higher level detail with our updating, put more information in regarding materials and systems and design. So many more pieces of investigation that will inform that, that it'll all, it'll all inform that. I just can't sort of look into a crystal ball and say, if we knew that Six projects went up and two projects went down.

[Member Jessica Parks]: But my point is like the more we're able to finalize things now, the easier it is to understand what a network cost is.

[Unidentified]: That is a very true statement.

[Member Jessica Parks]: Yes. That's more where I'm getting at is we have a number for what it would take to get to more we can finalize now. We will be able to understand what an actual number is and then work from there. And I think it's this nebulous, it's 99 here, but I think there's a concern from residents. What if it isn't? And I think that's where everyone needs. All of the things that keep happening are what keep us from getting to that concept. And I think that's where we just have to really hone in on exactly what the scope is forward. And that's kind of where I just want to encourage this group. Thank you. Thank you.

[Unidentified]: Zoe?

[Member Jenny Graham]: Zoe, are you able to unmute?

[Zoe Moutsos]: Yes. Sorry, I forgot to press unmute. Zoe Mutzos, 33 Johnson Ave. I just want to thank you all for your hard work. I just wanted to say I'm here in West Medford and I was at a community and neighborhood event this weekend with folks, none of whom have children, all of them are older than me and my son is in eighth grade and he will not have the benefit of the school that's going to be built. But all of everyone recognized that it needed to happen. And it happened to be a group of folks who are swimmers who are people involved in the community who go to the high school quite often. For different events that have nothing to do with the high school. And I think that was the hardest part for me when I started following along with this is really understanding how much this high school campus serves almost as a community center for the reasons that many people have said before, that we have had to move things to the high school space because we have made decisions in the past that the chickens are coming home to roost now. And so while this committee is working really hard to create the best learning environment for our students, our high school students, I really appreciate that you're not forgetting the rest of the community. And that also means our little ones with the Kids Corner and our MFM and MEEP and also the community and that you worked hard to make sure that the pool stayed and the gym continues and that we have good athletic fields. And I just wanna say, I know the number is big and everyone I've talked to, and I know it's gonna be hard. I mean, my kid's gonna be in college and I'll be paying for the school and college, but it's gonna be really hard to do. But I know, and I can see from everyone on this committee that you're committed to making this as reasonable as possible to get the best outcome as possible. And I'm just very excited to see how this is progressing. And I think the cuts that you showed today Uh, I mean, I was like, I actually said like, wow, that's really impressive. So I just want to say thank you.

[Luke Preisner]: Um, here in the room, David Bridge, I live in West Medford. Like I'm today as a resident, I'm speaking as a resident of it. So we're all, I don't want you to work. So a lot of people excited about the municipal, but the difference between what you need or what you want. And $7 million, I'm not clear if it's 750 or 700 million. 699. Yeah. That's the most expensive high school ever built anywhere in the United States. That is not true. That's not true. How many other high schools are there?

[Member Jenny Graham]: Brockton takes that brain from Massachusetts.

[Luke Preisner]: I believe that the piece that the residents here would pay, that's not compensated by the state. will be more than that. That's an issue. And so, um, I've already come here today. You guys are worth very hard, but I hear the discussions and I don't see the effort. It break, bring this down to a little point. I mean, listen, I need a new car and I would love to get a Mercedes Benz. It'll try to be very helpful. People love it. And down the road, there'll be one that but the cost is really needed. The cost will be significant. When I can get a Ford, and the Ford will also be expensive, but that will get me where I need to go. The students of Medford, the children here, they need to go to high school. But a Ford will get them there. There's no need for the Mercedes. I come from a neighborhood that's far wealthier than Medford. We never had anything like this. If we could afford it, that would be great. But the reality is the economics right now are very difficult and they're going to be more difficult. There will be other needs that the city will have. Police, teachers, fire, repairers, other things. And the burden of this particular school, the debt burden will be very significant for the residents. Everybody's excited about the high school. What I don't know is that this school, the new number, I have to figure it out. But the number you had before, which was $50,000 to $100 million, that was $60,000 per household. So this will be $48,000 to $50,000 over the 30 years. That's not a lot of money. That's a new roof. That's a new bar. That's a couple years of college tuition. That's food on the table. It's a significant thing. Yes, we didn't go to high school, but you could have done better. And Mr. Pressner was right. I would encourage you to go back to the table. make some cuts, this doesn't need to be divisive, it could be a win situation. The problem now is we get the high school, it's going to hurt the city dramatically. If we don't, it hurts the city dramatically. But it could be a win situation by scaling it down, get the kids where they'll go, get them where they need to go.

[Member Jenny Graham]: Your two minutes is up, so if you could wrap up your comments, I'm hungry. Is there anybody here waiting to speak? OK.

[SPEAKER_28]: Hi, my name is Susan Wilson. I live at 97 Winchester. Just really quickly, thank you guys so much for all the work that you've been doing. It's really clear how incredibly detailed you've been about, you know, how many 60 square foot bathrooms can we cut here and there. You're really doing granular work based on your extreme expertise in this arena, which many of us don't have, so I really appreciate you focusing on the tiniest square foot decisions to make this as affordable as possible. I think we're throwing the word affordability around a lot. And the truth is nothing is particularly affordable. And there's not a magic number that people want to pay. Nobody wants to pay anything. But that isn't possible. We live in a community. We live in a society. We have to fund the society that we live in. We're in a place where we've done generations of deferred maintenance. And the economy is garbage. And that's still a reality. It doesn't change the reality that we need a high school that is functional and legally up to code. There isn't a version of the school that somehow is cheap, that hits a magical number where everyone feels like, that is a number that I want to pay. Nobody who's been concerned about the affordability says, I would be thrilled with X amount to my taxes. So it feels like a moving target that is impossible to meet. I mean, cutting hundreds of millions of dollars that you guys have already cut is huge. It's a huge compromise. We're not getting a Mercedes. We're not getting a Lamborghini. We're getting, you know, a Corolla. It's just that Corollas are really expensive right now, and that's the reality. We can't cut things with no plan for where to put them. That's pretending that we have a future that doesn't exist either. We can't say, this high school can only be 9 to 12, then it's cheap, then we can afford it. all that other stuff is just extra. It's not extra. It's a core component of what makes Medford Medford. And to say it could be somewhere else, it doesn't have to be part of this process, is false. There's nowhere else for it to be. I would love to hear other proposals. If there's other ideas, that'd be great. But so far, it's been a lot of negativity and a lot of framing seniors against our kids, which is just, I think, not a reality of our actual neighbors. I think everyone's really feeling a lot of feelings about it, and that's tough. I don't love the idea of spending tax money either, but we have to, and it's for the greater good. And I want to support our neighbors as well. So I really, really appreciate all that you guys have been doing to get this as right-sized as possible. I think it's really an incredible compromise. And I appreciate all the work. And I think now it's our job to get the city to be excited about it, to really tell everybody about how awesome it is and to look into other options to make the impact on our final tax bills as small as possible. But now we're done cutting stuff. We need to be excited about the project that we have and the opportunity that it gives us. Thank you.

[Member Jenny Graham]: Thank you. Fritzie?

[SPEAKER_23]: Hi. Thanks so much. Fritzie Pieper at 34 Ross Street. I wanted to speak to including MFN, MEEP, and Kids Corner. Just sharing my own children and kids in our neighborhood have benefited immensely from these programs, I mean nearly on a weekly basis. and keeping these programs is a great opportunity for us to reap the benefits for the whole community. Not only are they named in the ed plan, they'll also help us meet the objectives of it. We'll be able to avoid having to do those projects later. Other people have spoken to this. So really, I feel strongly that you know, the work that the committee is doing to keeping these non-core programs with the high school is really important so that it doesn't result in the residents of this city having to pay even more to rehouse or relocate them in the future. And that kind of brings me to cost, right? I have three kids. I want to point out that cost implications for households is a huge factor for folks like myself that have young families. This truth isn't limited to just seniors or folks whose kids aren't school-aged anymore. But I also understand the time value of money, and it will cost us even more if we don't do this now. And so I'm very excited and so grateful for all the work that's been done already. I so appreciate the discussion and all the questions as detailed as they've been, um, that have been asked in the compromise that I've seen so far. So just thank you so much. And I'm looking forward to supporting the debt exclusion.

[Member Jenny Graham]: Thank you, Josh.

[Josh Terrill]: Hi, can you hear me? All right, very good. Thank you. Josh Terrell, 86 New Bern Avenue. Chair Graham, members of the committee, I just want to thank you for the opportunity to speak. I had prepared something different tonight. I expected to spend most of my time defending programs that were still on the table. Instead, I just want to say thank you. Since April, this committee has found roughly 70,000 square feet of efficiencies and about $100 million in cost reductions. That's real work, and it deserves recognition. There were cuts I did not agree with, I didn't get everything I wanted, and I don't think anybody did. But compromise has been at the center of this process. I'm a father of a Mississauga kindergartner with a three-year-old coming up behind him. So this project is very real to me. I'm excited that MEEP, MFN, the Teen Health Center, Music, the Arts, Special Education, and Vocational Education remain part of this vision. We've heard concerns tonight about costs, and I understand them, but in my neck of South Medford, I'm hearing excitement. People understand that this is a major investment. This new high school is not a Mercedes-Benz. If you've been paying attention to the many cuts and compromises, to echo my neighbor Susan, this is closer to a tricked-out Prius.

Waiting doesn't make the underlying need disappear. The high school still has to be replaced. These programs still need homes. Folks haven't yet figured out that voting no in June is going to be far more expensive in the long run than voting yes. I just really hope people recognize this work, and when the time comes, you can count me among the residents ready to knock on doors, get our community engaged, and make sure people understand just how hard you all worked. So thank you all for your time. I appreciate it.

[Member Jenny Graham]: Thank you. I just have a few comments, Michael, before we adjourn tonight. So I just want to say thank you to this committee. This committee has done real work. We have reduced the cost of this project $150 million or something thereabouts. That's real money. That's more money than I ever thought was going to be possible to pull out of this project. And Wilbur is happy. I think it's kind of a sign that the government is listening to the people around them. So to many people's points, there are a lot of things I didn't agree with along the way. And there are just lots and lots and lots of things that we could continue to sort of pick at and disagree with. However, this committee has done everything in its power to address the cost of the project. When we talk about affordability, there are two sides of that coin. Cost is one. We have done our work at this moment. The other side of that coin is how we pay for this. And that is where we have to be patient. We have to let the city's finance team do their work. That is happening in real time. It is actively happening on a weekly basis to be talking about all of the myriad of assumptions that go into how will we finance this? That sort of changes. Every time something crazy in the world happens, the price of steel changes, the interest rates change. All of the things are part of like evolving conversation. And this city has real to do to finish that. to finish that analysis so that we can collectively bring to the community the answers to the questions people are seeking is, how much will this cost me? That answer, we just don't know yet. And everybody who says they know the answer to that question, I am highly confident they're all wrong. Everyone is wrong because there are just too many moving parts for anybody to have all of those assumptions, everything from what is How many tiers of bonding are we going to do to finance this project? So what does that mean in year one versus year five? What are we assuming based on like the housing stock and how it's going to grow and change over the next 30 years? So there's a lot of work still to do. This committee has done its work as of now to control side of the cost that is in the purview committee. The city is doing their work to do the name. They just need a little bit more time. And to that end, I also want to mention that the city is looking at an analysis of PURTIS-TUFs to determine whether there is programming that can go into PURTIS-TUFs when R-TUF is not yet available and when it is.

It creates a situation where we can find cost savings. We will bring that to this committee deliberation. Left field and as you may know, that that is still to come and they are part of that work. All of that is being conditioned to increased set of community forums, training sessions between the school committee and the city council, all as we move toward really the next round of costing that's going to drive the budget for this project, which will not happen until January. So we'll have a lot of conversation about cost affordability, what those things mean to us, where we're heading between now and January. And then with our construction measure on board and the validation of all the issues that are happening, we will arrive at that number at the end of January and not sooner. And it's worth it for all of us to let the city take the time and get that right, because if they get it wrong, it impacts us all. So I just want to say thank you from me to the committee who have done the work that the community was assisting.

And with that, I will mention that our next full committee meeting here is on the 16th of November with a community forum on the 19th. And the scheduled joint listening sessions will be rolled out in the coming days. hopefully, an official press release so that we can separate back from the commission and let everybody know exactly what happened tonight and over the last handful of votes. And with that, I will ask if there is a motion to adjourn. I move to leave. I move to leave. By Nicole, seconded by Brian. Nicole de Rond. Jenny Camp. Yes. Mayor Londo Kern. Absent. Dr. Galuzzi. Yes. Marta Cabral. Yes. Ken Lord. Yes.

[SPEAKER_26]: Yes. Yes.

Jenny Graham

total time: 40.5 minutes
total words: 5135
Jessica Parks

total time: 2.32 minutes
total words: 355
Nick Giurleo

total time: 2.02 minutes
total words: 349
Breanna Lungo-Koehn

total time: 0.81 minutes
total words: 141
John Falco

total time: 4.49 minutes
total words: 630